Inlets ta T11F&g unit price, Illinois

Low bidders on IDOT contracts carried a median of $2,214.90 per EACH for item 60236800, inlets ta t11f&g, over the 24 months to 18 SEP 2026, across 40 low bids. Half of all 172 bids fell between $2,053.30 and $2,885.88.

Owner
Illinois DOT
Item
60236800
Unit
EACH
Latest letting
31 JUL 2026
$2,214.90Low bidder's median, per EACH
$2,440.00Median of all bids, per EACH
40Contracts in the window

By year of letting

Inlets ta T11F&g, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20211212$1,518.1481$1,650.00
20221717$1,742.0067$2,000.00
20232020$2,420.5077$2,250.00
20241818$2,325.0061$2,400.00
20252020$2,200.0085$2,354.00
20261313$2,200.0060$2,618.50
Inlets ta T11F&g, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Inlets ta T11F&g, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 0125$2,200.00134$2,426.57
District 036$1,962.5015$1,804.83
District 063$2,875.008$2,837.50
District 053$3,500.005$3,500.00
Inlets ta T11F&g, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Inlets ta T11F&g, IDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 210$2,350.00
2 to 410$2,200.00
4 to 810$2,497.50
9 to 3610$2,214.90
Inlets ta T11F&g, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Inlets ta T11F&g
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
31 JUL 202661K85District 0114$2,500.00$2,618.1610Plote Construction, Inc.IDOT
12 JUN 202661M44District 014$3,465.00$3,465.003Geske and Sons, Inc.IDOT
12 JUN 202662U72District 019$1,968.89$2,269.835Martam Construction IncorporatedIDOT
24 APR 202661L54District 0116$2,288.77$2,382.892Martam Construction IncorporatedIDOT
24 APR 202661M35District 012$2,180.00$2,750.005Landmark Contractors, Inc.IDOT
24 APR 202687899District 031$2,000.00$2,700.003Austin Tyler Construction, Inc.IDOT
27 FEB 202661M26District 017$2,800.00$2,706.004A Lamp Concrete Contractors, Inc.IDOT
27 FEB 202662R23District 013$2,200.00$2,250.003D. Construction, Inc. & Kraemer North America, LLC JVIDOT
16 JAN 202661K16District 011$2,030.00$2,766.0010Alliance Contractors, Inc.IDOT
16 JAN 202661L42District 012$2,813.00$2,630.005D'Land Construction, LLCIDOT
16 JAN 202661M08District 016$2,141.77$2,531.245Campanella and Sons, Inc.IDOT
16 JAN 202662W33District 018$2,195.00$2,397.502Iroquois Paving CorporationIDOT
16 JAN 202693839District 064$2,875.00$3,512.663Kinney Contractors, Inc.IDOT
19 SEP 202561L28District 015$1,609.06$2,150.004Martam Construction IncorporatedIDOT
19 SEP 202562R22District 012$2,200.00$1,937.383D. Construction, Inc.IDOT
Latest IDOT contracts carrying Inlets ta T11F&g

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy