Inlets ta T24F&g unit price, Illinois

Low bidders on IDOT contracts carried a median of $2,475.00 per EACH for item 60237470, inlets ta t24f&g, over the 24 months to 18 SEP 2026, across 42 low bids. Half of all 153 bids fell between $2,000.00 and $2,950.00.

Owner
Illinois DOT
Item
60237470
Unit
EACH
Latest letting
18 SEP 2026
$2,475.00Low bidder's median, per EACH
$2,400.00Median of all bids, per EACH
42Contracts in the window

By year of letting

Inlets ta T24F&g, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20211212$1,525.0057$1,508.01
20221515$2,200.0059$2,000.00
20232424$2,200.0083$2,100.00
20242626$2,249.00100$2,250.00
20251717$2,050.0061$2,250.00
20261919$2,500.0065$2,440.00
Inlets ta T24F&g, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Inlets ta T24F&g, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 0124$2,075.00108$2,170.00
District 0810$3,200.0030$2,748.00
District 033$1,900.008$2,050.00
Inlets ta T24F&g, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Inlets ta T24F&g, IDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 210$2,850.00
2 to 411$2,800.00
4 to 1510$2,587.50
20 to 11311$1,807.09
Inlets ta T24F&g, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Inlets ta T24F&g
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 SEP 202680D33District 012$1,600.00$1,610.003K-Five Construction CorporationIDOT
18 SEP 202697892District 084$3,500.00$3,738.213Plocher Construction Company, Inc.IDOT
31 JUL 202661K19District 011$4,785.00$3,642.504R. W. Dunteman CompanyIDOT
31 JUL 202661M13District 0135$1,780.55$1,790.286Dunnet Bay Construction CompanyIDOT
31 JUL 202662T84District 012$2,500.00$2,500.003D. Construction, Inc.IDOT
12 JUN 202662U72District 0139$1,807.09$2,110.305Martam Construction IncorporatedIDOT
12 JUN 202697827District 082$2,300.00$2,847.363Hank's Excavating & Landscaping, Inc.IDOT
24 APR 202661M15District 011$3,100.00$2,500.003Dunnet Bay Construction CompanyIDOT
24 APR 202680B76District 013$2,440.00$2,606.202D. Construction, Inc.IDOT
24 APR 202680C85District 01113$2,100.00$2,450.004Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc.IDOT
24 APR 202687899District 0323$1,900.00$2,550.003Austin Tyler Construction, Inc.IDOT
27 FEB 202668F91District 042$3,872.00$3,872.001Gunther Construction, a div of UCM, Inc.IDOT
27 FEB 202697872District 087$2,500.00$2,400.003DMS Contracting, Inc.IDOT
27 FEB 202697882District 085$3,700.00$3,050.002Stutz Excavating, Inc.IDOT
16 JAN 202661J01District 012$2,010.00$2,010.005R. W. Dunteman CompanyIDOT
Latest IDOT contracts carrying Inlets ta T24F&g

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy