P p conc dk bm 21 dp unit price, Illinois
Low bidders on IDOT contracts carried a median of $109.00 per SF for item 50400405, p p conc dk bm 21 dp, over the 24 months to 18 SEP 2026, across 13 low bids. Half of all 33 bids fell between $116.00 and $144.00.
- Owner
- Illinois DOT
- Item
- 50400405
- Unit
- SF
- Latest letting
- 24 APR 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 9 | 9 | $86.00 | 27 | $88.00 |
| 2022 | 13 | 13 | $92.00 | 40 | $98.00 |
| 2023 | 6 | 6 | $105.50 | 17 | $109.00 |
| 2024 | 10 | 10 | $107.00 | 32 | $116.00 |
| 2025 | 6 | 6 | $108.00 | 14 | $120.50 |
| 2026 | 6 | 6 | $123.70 | 16 | $129.20 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 795 to 1,318 | 3 | $144.00 |
| 1,344 to 1,510 | 3 | $109.00 |
| 1,593 to 2,800 | 3 | $118.00 |
| 3,568 to 5,780 | 4 | $105.70 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 24 APR 2026 | 89871 | District 04 | 1,593 | $108.00 | $115.50 | 2 | County Contractors, Inc. | IDOT |
| 27 FEB 2026 | 70H61 | District 05 | 795 | $220.00 | $261.38 | 2 | Stark Excavating, Inc. | IDOT |
| 27 FEB 2026 | 93845 | District 06 | 1,510 | $119.00 | $119.50 | 4 | Laverdiere Construction, Inc. | IDOT |
| 16 JAN 2026 | 46939 | District 04 | 2,192 | $128.40 | $128.40 | 1 | R. A. Cullinan and Son, a div of UCM, Inc. | IDOT |
| 16 JAN 2026 | 46943 | District 01 | 1,069 | $144.00 | $157.93 | 5 | Alliance Contractors, Inc. | IDOT |
| 16 JAN 2026 | 93849 | District 06 | 1,318 | $106.00 | $112.50 | 2 | County Contractors, Inc. | IDOT |
| 07 NOV 2025 | 46944 | District 02 | 1,444 | $109.00 | $114.00 | 3 | Martin & Company Excavating | IDOT |
| 07 NOV 2025 | 87889 | District 03 | 3,840 | $104.40 | $110.20 | 2 | D. Construction, Inc. | IDOT |
| 19 SEP 2025 | 74654 | District 07 | 3,568 | $107.00 | $116.00 | 2 | C-Hill Civil Contractors, Inc. | IDOT |
| 25 APR 2025 | 85773 | District 02 | 2,800 | $118.00 | $142.00 | 3 | Martin & Company Excavating | IDOT |
| 25 APR 2025 | 93829 | District 06 | 1,344 | $105.00 | $123.00 | 3 | County Contractors, Inc. | IDOT |
| 07 MAR 2025 | 87852 | District 03 | 3,961 | $127.00 | $127.00 | 1 | D. Construction, Inc. | IDOT |
| 08 NOV 2024 | 61H32 | District 01 | 5,780 | $104.00 | $120.00 | 3 | D. Construction, Inc. | IDOT |
| 02 AUG 2024 | 93809 | District 06 | 3,078 | $105.00 | $104.84 | 4 | County Contractors, Inc. | IDOT |
| 14 JUN 2024 | 91646 | District 05 | 1,458 | $105.00 | $105.00 | 3 | Stark Excavating, Inc. | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.