Stud shear connectors unit price, Illinois

Low bidders on IDOT contracts carried a median of $5.00 per EACH for item 50500505, stud shear connectors, over the 24 months to 18 SEP 2026, across 109 low bids. Half of all 329 bids fell between $4.00 and $12.10.

Owner
Illinois DOT
Item
50500505
Unit
EACH
Latest letting
18 SEP 2026
$5.00Low bidder's median, per EACH
$5.01Median of all bids, per EACH
109Contracts in the window

By year of letting

Stud shear connectors, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20214040$4.21141$4.84
20224949$4.74149$5.00
20234645$5.00123$4.75
20244848$5.00140$5.14
20254848$5.05141$5.10
20264747$4.76138$4.78
Stud shear connectors, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Stud shear connectors, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 0137$5.00147$5.00
District 029$5.7431$7.78
District 0710$4.7930$4.67
District 0913$4.0029$4.00
District 049$7.5022$5.81
District 0810$4.5820$4.65
District 039$5.0019$6.00
District 056$5.0016$5.00
District 066$13.4315$13.60
Stud shear connectors, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Stud shear connectors, IDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
8 to 1,11927$24.53
1,155 to 4,32027$5.00
4,785 to 11,36027$4.50
12,000 to 100,63728$4.50
Stud shear connectors, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Stud shear connectors
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 SEP 202666926District 031,704$5.00$6.002D. Construction, Inc.IDOT
18 SEP 202668E86District 042,988$5.00$6.153Stark Excavating, Inc.IDOT
18 SEP 202672406District 0674$27.20$55.003Freesen, a div of UCM, Inc.IDOT
18 SEP 202674650District 0715,102$4.43$4.753Sangamo Construction CompanyIDOT
18 SEP 202697892District 089,090$3.99$4.333Plocher Construction Company, Inc.IDOT
31 JUL 202662T84District 01116$10.00$25.003D. Construction, Inc.IDOT
31 JUL 202662W20District 018,757$4.00$3.886D. Construction, Inc.IDOT
12 JUN 202662L30District 01196$20.00$32.506D. Construction, Inc.IDOT
12 JUN 202662R61District 0127,684$4.40$4.403OHLA Central, Inc.IDOT
12 JUN 202664L94District 02308$45.00$35.004Valley Construction Co.IDOT
12 JUN 202666N45District 034,185$5.00$6.003D. Construction, Inc.IDOT
12 JUN 202670D62District 054,914$4.00$4.102William Charles Construction Company, LLCIDOT
12 JUN 202674705District 0722,610$5.20$4.613William Charles Construction Company, LLCIDOT
12 JUN 202676R32District 0810,188$4.65$4.802Stutz Excavating, Inc.IDOT
12 JUN 202678791District 094,032$4.00$3.922Samron Midwest Contracting, Inc.IDOT
Latest IDOT contracts carrying Stud shear connectors

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy