Test pile, dynamic, production unit price, Indiana

Low bidders on INDOT contracts carried a median of $85.00 per LFT for item 701-09557, test pile, dynamic, production, over the 24 months to 05 NOV 2026, across 51 low bids. Half of all 257 bids fell between $67.00 and $130.00.

Owner
Indiana DOT
Item
701-09557
Unit
LFT
Latest letting
07 OCT 2026
$85.00Low bidder's median, per LFT
$92.00Median of all bids, per LFT
51Contracts in the window

By year of letting

Test pile, dynamic, production, INDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20223131$88.44111$98.93
20232121$102.0058$94.85
20242222$77.5091$85.00
20252323$80.00125$94.63
20262020$91.0094$96.50
Test pile, dynamic, production, INDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Test pile, dynamic, production, INDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Greenfield14$70.0079$80.00
LaPorte12$97.9557$128.84
Fort Wayne9$92.0038$90.00
Crawfordsville6$82.5035$89.15
Vincennes5$90.0024$90.00
Seymour5$104.0024$76.30
Test pile, dynamic, production, INDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Test pile, dynamic, production, INDOT: low bidder's median by quantity band
Quantity (LFT)Low bidsLow-bid median
55 to 15612$78.50
157 to 22213$100.00
225 to 36713$75.00
368 to 85113$86.00
Test pile, dynamic, production, INDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest INDOT contracts carrying Test pile, dynamic, production
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
07 OCT 2026B-44483-AGreenfield124$72.00$119.006DUNCAN ROBERTSON INCINDOT
07 OCT 2026B-44620-AGreenfield156$100.00$100.007BRUMBAUGH CONSTRUCTION INCINDOT
02 SEP 2026B-42374-AFort Wayne632$56.00$61.003R L MCCOY INCINDOT
02 SEP 2026B-43771-ASeymour273$75.00$70.806DUNCAN ROBERTSON INCINDOT
02 SEP 2026B-44104-ALaPorte313$63.00$85.004MILESTONE CONTRACTORS LPINDOT
02 SEP 2026B-44107-ALaPorte88$145.00$148.006ELLAS CONSTRUCTION COMPANY INCINDOT
02 SEP 2026B-44108-ALaPorte366$100.00$130.007ELLAS CONSTRUCTION COMPANY INCINDOT
02 SEP 2026B-44287-AVincennes368$90.00$92.504CLR, INC.INDOT
02 SEP 2026B-44507-AVincennes210$100.00$100.003RAGLE, INC.INDOT
05 AUG 2026B-44526-AFort Wayne155$92.00$93.502MILESTONE CONTRACTORS LPINDOT
08 JUL 2026B-42442-ALaPorte851$150.00$147.504DUNNET BAY CONSTRUCTION COMPANYINDOT
08 JUL 2026B-44244-ACrawfordsville222$70.00$99.507DUNCAN ROBERTSON INCINDOT
08 JUL 2026B-44515-AFort Wayne159$155.00$90.005MILESTONE CONTRACTORS LPINDOT
08 JUL 2026B-45531-AFort Wayne261$98.00$81.504MILESTONE CONTRACTORS LPINDOT
08 APR 2026B-40891-ASeymour290$117.00$100.587FORCE CONSTRUCTION CO INCINDOT
Latest INDOT contracts carrying Test pile, dynamic, production

Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.

How these prices were read

INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy