Topsoil amendment budget unit price, Indiana

Low bidders on INDOT contracts carried a median of $1.00 per DOL for item 629-000150, topsoil amendment budget, over the 24 months to 05 NOV 2026, across 102 low bids. Half of all 432 bids fell between $1.00 and $1.00.

Owner
Indiana DOT
Item
629-000150
Unit
DOL
Latest letting
05 NOV 2026
$1.00Low bidder's median, per DOL
$1.00Median of all bids, per DOL
102Contracts in the window

By year of letting

Topsoil amendment budget, INDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20251717$1.0080$1.00
20268585$1.00352$1.00
Topsoil amendment budget, INDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Topsoil amendment budget, INDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Greenfield20$1.00112$1.00
Seymour20$1.0095$1.00
LaPorte22$1.0076$1.00
Vincennes18$1.0060$1.00
Crawfordsville12$1.0051$1.00
Fort Wayne9$1.0033$1.00
Topsoil amendment budget, INDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Topsoil amendment budget, INDOT: low bidder's median by quantity band
Quantity (DOL)Low bidsLow-bid median
2,224 to 6,50025$1.00
7,024 to 13,183.7826$1.00
13,312 to 21,210.6125$1.00
21,350.44 to 502,90626$1.00
Topsoil amendment budget, INDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest INDOT contracts carrying Topsoil amendment budget
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
05 NOV 2026R-39073-AGreenfield14,930$1.00$1.007MORPHEY CONSTRUCTION, INC.INDOT
05 NOV 2026R-42227-AGreenfield8,740$1.00$1.007RIETH-RILEY CONSTRUCTION CO., INC.INDOT
05 NOV 2026R-43809-ALaPorte13,676$1.00$1.003F.H. PASCHEN, S.N. NIELSEN & ASSOCIATES LLCINDOT
05 NOV 2026R-44008-ALaPorte5,664$1.00$1.003GARIUP CONSTRUCTION CO., INC.INDOT
05 NOV 2026R-44293-ASeymour5,170$1.00$1.007RIVER TOWN CONSTRUCTION, LLCINDOT
05 NOV 2026R-46447-ALaPorte6,166$1.00$1.003MILESTONE CONTRACTORS LPINDOT
05 NOV 2026T-46195-ACrawfordsville12,409$1.00$1.003RIETH-RILEY CONSTRUCTION CO., INC.INDOT
07 OCT 2026R-43027-CLaPorte11,342$1.00$1.002RIETH-RILEY CONSTRUCTION CO., INC.INDOT
07 OCT 2026R-43918-ALaPorte66,734.05$1.00$1.003F.H. PASCHEN, S.N. NIELSEN & ASSOCIATES LLCINDOT
07 OCT 2026R-44109-ALaPorte6,251$1.00$1.004RIETH-RILEY CONSTRUCTION CO., INC.INDOT
07 OCT 2026R-44721-ASeymour19,500$1.00$1.004MILESTONE CONTRACTORS LPINDOT
07 OCT 2026B-43499-AGreenfield62,006$1.00$1.006MILESTONE CONTRACTORS LPINDOT
07 OCT 2026B-43637-ASeymour3,554$1.00$1.008DUNCAN ROBERTSON INCINDOT
07 OCT 2026B-44486-AGreenfield2,646$1.00$1.005MILESTONE CONTRACTORS LPINDOT
07 OCT 2026B-44619-AGreenfield10,420$1.00$1.006DUNCAN ROBERTSON INCINDOT
Latest INDOT contracts carrying Topsoil amendment budget

Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.

How these prices were read

INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy