Concrete-class aa unit price, Kentucky
Low bidders on KYTC contracts carried a median of $1,600.00 per CY for concrete-class aa, over the 24 months to 22 OCT 2026, across 11 low bids. Half of all 44 bids fell between $1,403.25 and $2,000.00.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- CY
- Latest letting
- 24 OCT 2024
$1,600.00Low bidder's median, per CY
$1,665.00Median of all bids, per CY
8Contracts in the window
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2019 | 3 | 6 | $1,701.76 | 14 | $1,853.62 |
| 2020 | 30 | 39 | $900.00 | 174 | $1,190.00 |
| 2021 | 44 | 62 | $1,175.00 | 244 | $1,200.00 |
| 2022 | 47 | 75 | $1,500.00 | 236 | $2,025.00 |
| 2023 | 63 | 89 | $2,000.00 | 299 | $2,156.42 |
| 2024 | 57 | 71 | $1,500.00 | 282 | $1,750.00 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 24 OCT 2024 | 24-5366 | District 11 | 78.60 | $1,250.00 | $1,575.00 | 7 | KAY & KAY CONTRACTING LLC | KYTC |
| 24 OCT 2024 | 24-1318 | District 2 | 148.30 | $1,300.00 | $1,375.00 | 2 | SCOTT AND MURPHY INC | KYTC |
| 24 OCT 2024 | 24-1318 | District 2 | 140.70 | $1,353.00 | $1,401.50 | 2 | SCOTT AND MURPHY INC | KYTC |
| 24 OCT 2024 | 24-1318 | District 2 | 82.80 | $1,716.00 | $1,703.00 | 2 | SCOTT AND MURPHY INC | KYTC |
| 24 OCT 2024 | 24-1318 | District 2 | 100 | $2,000.00 | $1,845.00 | 2 | SCOTT AND MURPHY INC | KYTC |
| 24 OCT 2024 | 24-5365 | District 2 | 40 | $1,978.00 | $2,275.00 | 4 | GALUSHA CONTRACTING LLC | KYTC |
| 24 OCT 2024 | 24-2958 | District 4 | 41.10 | $2,051.00 | $2,275.50 | 8 | GALUSHA CONTRACTING LLC | KYTC |
| 24 OCT 2024 | 24-2957 | District 4 | 389.70 | $1,150.00 | $1,450.00 | 7 | E AND B PAVING LLC | KYTC |
| 24 OCT 2024 | 24-1111 | District 2 | 7 | $3,750.00 | $3,750.00 | 1 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 24 OCT 2024 | 24-2962 | District 3 | 48.60 | $1,600.00 | $1,600.00 | 5 | CAMBRY CONTRACTING INC | KYTC |
| 24 OCT 2024 | 24-2997 | District 6 | 11.50 | $905.00 | $1,200.00 | 4 | M & M SERVICES CO INC | KYTC |
| 26 SEP 2024 | 24-5361 | District 2 | 36.10 | $2,042.00 | $2,500.00 | 3 | GALUSHA CONTRACTING LLC | KYTC |
| 26 SEP 2024 | 24-5363 | District 8 | 58.40 | $1,920.00 | $1,920.00 | 5 | CENTRAL BRIDGE CO LLC | KYTC |
| 26 SEP 2024 | 24-2955 | District 2 | 32.50 | $3,500.00 | $5,075.00 | 2 | M & M SERVICES CO INC | KYTC |
| 26 SEP 2024 | 24-2995 | District 3 | 61.70 | $1,490.69 | $1,319.85 | 4 | SCOTT AND MURPHY INC | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.