Conduit-1 1/4 in unit price, Kentucky

Low bidders on KYTC contracts carried a median of $7.18 per LF A A for conduit-1 1/4 in, over the 24 months to 22 OCT 2026, across 69 low bids. Half of all 134 bids fell between $7.17 and $12.80.

Owner
Kentucky Transportation Cabinet
Item
No code published
Unit
LF A A
Latest letting
22 OCT 2026
$7.18Low bidder's median, per LF A A
$8.07Median of all bids, per LF A A
48Contracts in the window

By year of letting

Conduit-1 1/4 in, KYTC: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20252529$8.0061$8.00
20262340$7.1773$8.13
Conduit-1 1/4 in, KYTC: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Conduit-1 1/4 in, KYTC: low bidder's median by quantity band
Quantity (LF A A)Low bidsLow-bid median
10 to 4017$7.40
50 to 6017$7.17
60 to 8017$8.00
80 to 75018$8.13
Conduit-1 1/4 in, KYTC: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest KYTC contracts carrying Conduit-1 1/4 in
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
22 OCT 202626-216260$25.00$25.005HALL CONTRACTING OF KENTUCKY INCKYTC
22 OCT 202626-255610$18.49$18.496HALL CONTRACTING OF KENTUCKY INCKYTC
24 SEP 202626-224040$8.95$8.955E & B PAVING LLCKYTC
03 SEP 202626-218515$17.63$17.632L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTIONKYTC
03 SEP 202626-212150$8.13$19.572H G MAYS CORPORATIONKYTC
03 SEP 202626-213680$8.13$8.134LOUISVILLE PAVING COMPANY INCKYTC
03 SEP 202626-222480$8.13$8.131MOUNTAIN ENTERPRISES INCKYTC
20 AUG 202626-151780$8.17$8.172L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTIONKYTC
20 AUG 202626-204090$7.50$7.501SCOTTY'S CONTRACTING & STONE LLCKYTC
20 AUG 202626-220540$8.13$8.132HINKLE CONTRACTING COMPANY LLCKYTC
20 AUG 202626-217280$23.00$23.001WALKER CONSTRUCTION & MATERIALS LLCKYTC
21 MAY 202626-111880$8.00$7.884EATON ASPHALT PAVING CO INCKYTC
23 APR 202626-440150$7.45$21.435HALL CONTRACTING OF KENTUCKY INCKYTC
26 MAR 202626-111160$7.17$7.171DAVIS H ELLIOT CONSTRUCTION COMPANY INCKYTC
26 MAR 202626-111160$7.17$7.171DAVIS H ELLIOT CONSTRUCTION COMPANY INCKYTC
Latest KYTC contracts carrying Conduit-1 1/4 in

Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.

How these prices were read

KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy