Culvert pipe-30 in unit price, Kentucky
Low bidders on KYTC contracts carried a median of $175.51 per LF for culvert pipe-30 in, from 24 JUL 2020 to 22 AUG 2024, across 94 low bids. Half of all 190 bids fell between $124.25 and $230.78.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- LF
- Latest letting
- 22 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 5 | 5 | $108.30 | 22 | $104.15 |
| 2021 | 27 | 28 | $162.03 | 76 | $161.58 |
| 2022 | 34 | 34 | $169.50 | 45 | $175.00 |
| 2023 | 18 | 18 | $235.66 | 22 | $220.69 |
| 2024 | 9 | 9 | $120.20 | 25 | $172.01 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 5 | 8 | $150.00 | 27 | $160.00 |
| District 4 | 10 | $169.50 | 25 | $129.67 |
| District 3 | 11 | $183.29 | 23 | $224.00 |
| District 10 | 9 | $151.32 | 20 | $134.00 |
| District 7 | 11 | $185.00 | 17 | $164.00 |
| District 8 | 6 | $161.00 | 15 | $150.00 |
| District 2 | 10 | $177.83 | 15 | $190.00 |
| District 12 | 8 | $411.45 | 13 | $263.80 |
| District 6 | 7 | $280.00 | 13 | $141.67 |
| District 9 | 5 | $315.00 | 10 | $240.00 |
| District 1 | 4 | $111.04 | 7 | $96.21 |
| District 11 | 5 | $180.00 | 5 | $180.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 4 to 46 | 23 | $300.00 |
| 46 to 108 | 24 | $182.50 |
| 112 to 181 | 23 | $168.00 |
| 185 to 1,046 | 24 | $138.96 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 AUG 2024 | 24-1011 | District 11 | 89 | $180.00 | $180.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 18 JUL 2024 | 24-1313 | District 6 | 157 | $280.00 | $155.41 | 4 | RIEGLER BLACKTOP INC | KYTC |
| 20 JUN 2024 | 24-1107 | District 4 | 185 | $104.41 | $129.67 | 5 | HINKLE CONSTRUCTION SERVICES LLC | KYTC |
| 20 JUN 2024 | 24-1312 | District 4 | 253 | $106.68 | $300.00 | 3 | LOUISVILLE PAVING COMPANY INC | KYTC |
| 23 MAY 2024 | 24-1105 | District 5 | 143 | $120.00 | $173.50 | 6 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 21 MAR 2024 | 24-1306 | District 10 | 58 | $88.88 | $88.88 | 1 | TRITON CONSTRUCTION INC | KYTC |
| 21 MAR 2024 | 24-1301 | District 1 | 316 | $120.20 | $120.20 | 1 | JIM SMITH CONTRACTING COMPANY LLC | KYTC |
| 21 MAR 2024 | 24-1006 | District 2 | 44 | $277.79 | $298.89 | 2 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 22 FEB 2024 | 24-1303 | District 2 | 156 | $305.00 | $228.08 | 2 | CLEARY CONSTRUCTION INC | KYTC |
| 14 DEC 2023 | 23-1043 | District 4 | 283 | $216.38 | $185.69 | 2 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 26 OCT 2023 | 23-1340 | District 7 | 152 | $200.00 | $200.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 26 OCT 2023 | 23-2401 | District 10 | 40 | $375.95 | $375.95 | 1 | MOUNTAIN ENTERPRISES INC | KYTC |
| 28 SEP 2023 | 23-1316 | District 11 | 314 | $180.00 | $180.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 22 JUN 2023 | 23-1104 | District 5 | 14 | $300.00 | $262.50 | 2 | MAC CONSTRUCTION & EXCAVATING INC | KYTC |
| 22 JUN 2023 | 23-1326 | District 2 | 20 | $190.98 | $190.98 | 1 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.