Curb box inlet type a unit price, Kentucky
Low bidders on KYTC contracts carried a median of $6,800.00 per EACH for curb box inlet type a, from 22 NOV 2019 to 26 SEP 2024, across 73 low bids. Half of all 180 bids fell between $5,275.00 and $8,191.70.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- EACH
- Latest letting
- 26 SEP 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2019 | 2 | 2 | $5,032.50 | 5 | $6,000.00 |
| 2020 | 12 | 12 | $5,950.00 | 37 | $5,400.00 |
| 2021 | 12 | 12 | $5,031.50 | 44 | $5,250.00 |
| 2022 | 20 | 20 | $7,600.00 | 26 | $7,980.00 |
| 2023 | 14 | 14 | $7,881.47 | 31 | $8,545.00 |
| 2024 | 13 | 13 | $7,050.00 | 37 | $7,213.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 6 | 12 | $6,453.72 | 43 | $6,607.44 |
| District 5 | 10 | $8,739.68 | 35 | $9,000.00 |
| District 7 | 12 | $7,275.00 | 21 | $6,000.00 |
| District 4 | 6 | $6,735.68 | 17 | $6,000.00 |
| District 11 | 12 | $6,925.00 | 17 | $6,700.00 |
| District 10 | 3 | $5,086.00 | 11 | $5,086.00 |
| District 12 | 4 | $6,539.97 | 9 | $6,500.00 |
| District 1 | 5 | $6,751.97 | 8 | $6,066.25 |
| District 8 | 3 | $7,213.00 | 5 | $7,213.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 3 | 18 | $7,342.18 |
| 3 to 10 | 18 | $7,397.59 |
| 12 to 43 | 18 | $5,950.00 |
| 50 to 159 | 19 | $6,500.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 SEP 2024 | 24-4106 | District 11 | 1 | $7,050.00 | $7,050.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 22 AUG 2024 | 24-1009 | District 12 | 6 | $5,500.00 | $5,500.00 | 3 | FREDERICK & MAY CONSTRUCTION CO | KYTC |
| 18 JUL 2024 | 24-1313 | District 6 | 25 | $9,300.00 | $8,125.42 | 4 | RIEGLER BLACKTOP INC | KYTC |
| 20 JUN 2024 | 24-1107 | District 4 | 2 | $7,471.35 | $8,000.00 | 5 | HINKLE CONSTRUCTION SERVICES LLC | KYTC |
| 20 JUN 2024 | 24-4103 | District 8 | 1 | $7,213.00 | $7,213.00 | 1 | HINKLE CONTRACTING COMPANY LLC | KYTC |
| 23 MAY 2024 | 24-1105 | District 5 | 1 | $7,000.00 | $8,234.81 | 6 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 23 MAY 2024 | 24-1311 | District 10 | 14 | $5,500.00 | $6,280.55 | 4 | FREDERICK & MAY CONSTRUCTION CO | KYTC |
| 25 APR 2024 | 24-4102 | District 8 | 1 | $17,877 | $17,877 | 1 | HINKLE CONTRACTING COMPANY LLC | KYTC |
| 21 MAR 2024 | 24-1306 | District 10 | 66 | $5,086.00 | $5,086.00 | 1 | TRITON CONSTRUCTION INC | KYTC |
| 21 MAR 2024 | 24-1004 | District 4 | 1 | $8,000.00 | $7,800.00 | 2 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 21 MAR 2024 | 24-1302 | District 2 | 76 | $7,750.00 | $9,375.00 | 2 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 21 MAR 2024 | 24-1309 | District 12 | 16 | $1,544.00 | $6,500.00 | 3 | BUSH & BURCHETT INC | KYTC |
| 22 FEB 2024 | 24-1305 | District 6 | 96 | $5,700.00 | $7,445.00 | 4 | EATON ASPHALT PAVING CO INC | KYTC |
| 16 NOV 2023 | 23-1109 | District 5 | 7 | $7,500.00 | $9,000.00 | 5 | FLYNN BROTHERS CONTRACTING INC | KYTC |
| 26 OCT 2023 | 23-1340 | District 7 | 102 | $8,500.00 | $8,500.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.