Guardrail connector to bridge end ty a unit price, Kentucky
Low bidders on KYTC contracts carried a median of $3,000.00 per EACH for guardrail connector to bridge end ty a, from 22 NOV 2019 to 20 JUN 2024, across 107 low bids. Half of all 202 bids fell between $2,450.00 and $3,359.28.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- EACH
- Latest letting
- 20 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2019 | 3 | 5 | $1,960.83 | 11 | $1,960.99 |
| 2020 | 21 | 21 | $2,450.00 | 57 | $2,500.00 |
| 2021 | 28 | 28 | $2,800.00 | 57 | $2,600.00 |
| 2022 | 27 | 27 | $3,357.11 | 42 | $3,339.38 |
| 2023 | 21 | 21 | $3,468.10 | 28 | $3,488.42 |
| 2024 | 4 | 5 | $3,485.03 | 7 | $3,485.03 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 1 | 14 | $2,800.00 | 26 | $2,734.95 |
| District 2 | 13 | $2,893.75 | 25 | $2,800.00 |
| District 9 | 8 | $2,400.00 | 23 | $2,400.00 |
| District 7 | 18 | $3,430.00 | 23 | $3,360.00 |
| District 5 | 7 | $3,488.58 | 21 | $3,409.92 |
| District 6 | 12 | $2,937.88 | 20 | $2,855.32 |
| District 12 | 3 | $2,400.00 | 14 | $2,400.00 |
| District 4 | 6 | $2,750.00 | 12 | $2,750.00 |
| District 3 | 7 | $2,500.00 | 12 | $2,315.95 |
| District 10 | 7 | $3,500.00 | 11 | $3,500.00 |
| District 11 | 8 | $3,318.56 | 10 | $3,172.20 |
| District 8 | 4 | $3,255.00 | 5 | $3,255.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 26 | $3,334.87 |
| 2 to 4 | 27 | $2,500.00 |
| 4 to 6 | 27 | $2,980.00 |
| 6 to 62 | 27 | $3,202.16 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 JUN 2024 | 24-5355 | District 1 | 2 | $3,204.31 | $3,204.31 | 2 | HAL COFFEY CONTRACTING LLC | KYTC |
| 21 MAR 2024 | 24-1005 | District 7 | 3 | $3,182.07 | $3,182.07 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 21 MAR 2024 | 24-1005 | District 7 | 3 | $3,513.19 | $3,513.19 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 25 JAN 2024 | 24-1304 | District 1 | 3 | $3,485.03 | $3,485.03 | 1 | JIM SMITH CONTRACTING COMPANY LLC | KYTC |
| 25 JAN 2024 | 24-4400 | District 7 | 8 | $3,545.26 | $3,736.36 | 2 | MAC CONSTRUCTION & EXCAVATING INC | KYTC |
| 14 DEC 2023 | 23-1047 | District 10 | 1 | $4,000.00 | $4,000.00 | 2 | HINKLE CONTRACTING COMPANY LLC | KYTC |
| 14 DEC 2023 | 23-5329 | District 5 | 2 | $4,200.00 | $4,349.32 | 4 | LOUISVILLE PAVING COMPANY INC | KYTC |
| 14 DEC 2023 | 23-2497 | District 11 | 2 | $3,064.40 | $3,064.40 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 16 NOV 2023 | 23-4420 | District 7 | 8 | $5,391.76 | $5,391.76 | 1 | HINKLE CONSTRUCTION SERVICES LLC | KYTC |
| 16 NOV 2023 | 23-4417 | District 7 | 4 | $3,360.00 | $3,360.00 | 1 | THE ALLEN COMPANY INC | KYTC |
| 26 OCT 2023 | 23-1341 | District 7 | 4 | $3,143.24 | $3,143.24 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 26 OCT 2023 | 23-1105 | District 7 | 1 | $7,005.43 | $8,017.72 | 2 | LOUISVILLE PAVING COMPANY INC | KYTC |
| 26 OCT 2023 | 23-2438 | District 11 | 4 | $3,500.00 | $3,500.00 | 1 | GEORGE B STONE CO LLC | KYTC |
| 28 SEP 2023 | 23-1316 | District 11 | 11 | $4,500.00 | $4,500.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 28 SEP 2023 | 23-4416 | District 7 | 8 | $5,840.47 | $5,840.47 | 1 | HINKLE CONSTRUCTION SERVICES LLC | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.