Guardrail end treatment type 4A unit price, Kentucky

Low bidders on KYTC contracts carried a median of $4,193.65 per EACH for guardrail end treatment type 4a, over the 24 months to 22 OCT 2026, across 1 low bids. Half of all 2 bids fell between $4,193.65 and $4,193.65.

Owner
Kentucky Transportation Cabinet
Item
No code published
Unit
EACH
Latest letting
24 OCT 2024
$4,193.65Low bidder's median, per EACH
$4,193.65Median of all bids, per EACH
1Contracts in the window

By year of letting

Guardrail end treatment type 4A, KYTC: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201933$2,408.028$2,250.00
20202121$2,200.0076$2,200.00
20214646$2,800.00107$2,800.00
20226060$4,000.0080$4,000.00
20234747$4,100.0074$4,193.22
20241515$4,346.0039$4,533.58
Guardrail end treatment type 4A, KYTC: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Guardrail end treatment type 4A, KYTC: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 520$4,011.4755$3,900.00
District 1123$4,000.0049$4,000.00
District 419$3,500.0041$3,487.08
District 622$3,954.7538$3,927.38
District 1012$3,300.0037$3,100.00
District 922$3,400.0036$3,100.00
District 217$3,375.7133$3,200.00
District 1216$4,000.0031$4,000.00
District 718$4,047.5023$4,000.00
District 19$2,918.4322$2,918.43
District 88$3,500.0012$3,500.00
District 36$2,870.307$2,800.00
Guardrail end treatment type 4A, KYTC: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Guardrail end treatment type 4A, KYTC: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 248$4,000.00
2 to 348$3,487.08
3 to 648$4,000.00
6 to 2848$3,500.00
Guardrail end treatment type 4A, KYTC: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest KYTC contracts carrying Guardrail end treatment type 4A
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
24 OCT 202424-1318District 217$4,193.65$4,193.652SCOTT AND MURPHY INCKYTC
26 SEP 202424-4202District 72$4,284.00$4,257.272THE ALLEN COMPANY INCKYTC
22 AUG 202424-1011District 119$4,110.87$4,110.871L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTIONKYTC
22 AUG 202424-5362District 14$4,529.14$4,529.143JIM SMITH CONTRACTING COMPANY LLCKYTC
22 AUG 202424-2299District 111$4,200.00$4,600.002N H STONE INCKYTC
18 JUL 202424-1108District 36$4,533.58$4,533.581SCOTTY'S CONTRACTING & STONE LLCKYTC
20 JUN 202424-1312District 45$4,193.65$4,193.653LOUISVILLE PAVING COMPANY INCKYTC
20 JUN 202424-2231District 111$5,000.00$5,000.001GEORGE B STONE CO LLCKYTC
21 MAR 202424-1005District 73$4,193.65$4,193.651L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTIONKYTC
21 MAR 202424-2979District 123$5,972.69$5,972.697FREDERICK & MAY CONSTRUCTION COKYTC
21 MAR 202424-1301District 14$4,705.76$4,705.761JIM SMITH CONTRACTING COMPANY LLCKYTC
21 MAR 202424-5341District 111$5,000.00$4,800.006INTECH CONTRACTING LLCKYTC
22 FEB 202424-1305District 61$4,346.00$4,439.794EATON ASPHALT PAVING CO INCKYTC
22 FEB 202424-1303District 25$4,705.76$4,981.412CLEARY CONSTRUCTION INCKYTC
25 JAN 202424-3001District 61$4,306.15$4,306.153MAC CONSTRUCTION & EXCAVATING INCKYTC
Latest KYTC contracts carrying Guardrail end treatment type 4A

Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.

How these prices were read

KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way