Guardrail end treatment type 7 unit price, Kentucky
Low bidders on KYTC contracts carried a median of $1,866.36 per EACH for guardrail end treatment type 7, over the 24 months to 22 OCT 2026, across 4 low bids. Half of all 16 bids fell between $1,857.60 and $2,518.75.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- EACH
- Latest letting
- 24 OCT 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2019 | 2 | 2 | $1,191.51 | 4 | $1,183.01 |
| 2020 | 42 | 43 | $1,260.00 | 125 | $1,274.97 |
| 2021 | 71 | 75 | $1,500.00 | 188 | $1,500.00 |
| 2022 | 65 | 65 | $1,800.00 | 140 | $1,800.00 |
| 2023 | 59 | 62 | $1,742.54 | 145 | $1,852.24 |
| 2024 | 34 | 34 | $1,857.60 | 126 | $1,923.70 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 12 | 109 | $1,700.00 | 268 | $1,750.00 |
| District 11 | 45 | $1,600.00 | 107 | $1,800.00 |
| District 4 | 18 | $1,604.93 | 54 | $1,605.34 |
| District 10 | 12 | $1,687.55 | 44 | $1,694.09 |
| District 6 | 13 | $1,590.00 | 42 | $1,595.00 |
| District 9 | 14 | $1,275.00 | 40 | $1,300.00 |
| District 8 | 14 | $1,725.00 | 40 | $1,704.79 |
| District 7 | 16 | $1,467.50 | 33 | $1,400.00 |
| District 3 | 11 | $1,493.70 | 27 | $1,500.00 |
| District 1 | 12 | $1,500.00 | 27 | $1,500.00 |
| District 2 | 10 | $1,570.43 | 27 | $1,570.43 |
| District 5 | 7 | $1,670.78 | 19 | $1,749.89 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 70 | $1,590.00 |
| 2 to 2 | 70 | $1,570.43 |
| 3 to 5 | 70 | $1,587.22 |
| 5 to 37 | 71 | $1,560.80 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 24 OCT 2024 | 24-1015 | District 8 | 4 | $1,857.60 | $1,857.60 | 4 | ROCK & DIRT LLC | KYTC |
| 24 OCT 2024 | 24-2344 | District 4 | 4 | $1,500.00 | $2,250.00 | 3 | GEORGE B STONE CO LLC | KYTC |
| 24 OCT 2024 | 24-1317 | District 11 | 2 | $3,084.00 | $2,676.47 | 6 | BOCA ENTERPRISES INC | KYTC |
| 24 OCT 2024 | 24-2323 | District 10 | 1 | $1,875.11 | $1,875.00 | 3 | N W K CONSTRUCTION INC | KYTC |
| 26 SEP 2024 | 24-5363 | District 8 | 3 | $1,857.60 | $1,857.60 | 5 | CENTRAL BRIDGE CO LLC | KYTC |
| 26 SEP 2024 | 24-2995 | District 3 | 4 | $3,616.75 | $1,948.32 | 4 | SCOTT AND MURPHY INC | KYTC |
| 22 AUG 2024 | 24-2952 | District 6 | 3 | $1,800.00 | $1,929.78 | 6 | M & M SERVICES CO INC | KYTC |
| 22 AUG 2024 | 24-2299 | District 11 | 24 | $2,500.00 | $2,250.00 | 2 | N H STONE INC | KYTC |
| 18 JUL 2024 | 24-5358 | District 6 | 2 | $1,685.00 | $1,740.00 | 8 | HINKLE CONSTRUCTION SERVICES LLC | KYTC |
| 18 JUL 2024 | 24-5356 | District 5 | 3 | $2,100.00 | $2,200.00 | 6 | HALL CONTRACTING OF KENTUCKY INC | KYTC |
| 18 JUL 2024 | 24-5360 | District 12 | 1 | $1,759.72 | $1,800.00 | 5 | FREDERICK & MAY CONSTRUCTION CO | KYTC |
| 18 JUL 2024 | 24-2256 | District 12 | 2 | $2,000.00 | $2,000.00 | 3 | HINKLE ENVIRONMENTAL SERVICES LLC | KYTC |
| 20 JUN 2024 | 24-1312 | District 4 | 3 | $1,692.04 | $1,692.04 | 3 | LOUISVILLE PAVING COMPANY INC | KYTC |
| 20 JUN 2024 | 24-2231 | District 11 | 24 | $2,000.00 | $2,000.00 | 1 | GEORGE B STONE CO LLC | KYTC |
| 23 MAY 2024 | 24-5350 | District 11 | 2 | $1,861.25 | $1,935.70 | 7 | IRVINE CONTRACTING LIMITED LIABILITY COMPANY | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.