36 in. surface-mount delineator post unit price, Missouri
Low bidders on MoDOT contracts carried a median of $107.00 per EACH for item 9031242, 36 in. surface-mount delineator post, over the 24 months to 16 OCT 2026, across 25 low bids. Half of all 73 bids fell between $92.86 and $150.00.
- Owner
- Missouri DOT
- Item
- 9031242
- Unit
- EACH
- Latest letting
- 15 MAY 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 2 | 2 | $78.75 | 8 | $75.00 |
| 2022 | 12 | 13 | $87.00 | 28 | $87.00 |
| 2023 | 13 | 13 | $100.00 | 45 | $100.00 |
| 2024 | 8 | 9 | $102.20 | 26 | $102.42 |
| 2025 | 14 | 15 | $108.15 | 45 | $110.00 |
| 2026 | 7 | 7 | $105.00 | 18 | $99.88 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Southwest | 7 | $99.75 | 19 | $102.20 |
| St. Louis | 5 | $180.00 | 18 | $152.50 |
| Central | 6 | $100.00 | 16 | $98.00 |
| Northeast | 3 | $243.00 | 6 | $189.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 8 | 6 | $176.25 |
| 10 to 15 | 6 | $107.58 |
| 17 to 35 | 6 | $102.50 |
| 59 to 200 | 7 | $100.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 15 MAY 2026 | 260515-C14 | Kansas City | 8 | $172.50 | $117.00 | 3 | Realm Construction Inc. | MoDOT |
| 15 MAY 2026 | 260515-G02 | Southwest | 27 | $99.75 | $99.75 | 1 | Midwest Traffic Signal Services, LLC | MoDOT |
| 17 APR 2026 | 260417-G01 | Southwest | 12 | $70.55 | $67.00 | 4 | Radmacher Brothers Excavating Co., Inc. | MoDOT |
| 20 MAR 2026 | 260320-H02 | Southeast | 17 | $105.00 | $105.00 | 3 | Lappe Cement Finishing, Inc. | MoDOT |
| 20 FEB 2026 | 260220-D01 | Central | 14 | $107.00 | $96.00 | 3 | Watson Concrete, Inc. | MoDOT |
| 20 FEB 2026 | 260220-G01 | Southwest | 102 | $125.00 | $125.00 | 2 | Hartman and Company, Inc. | MoDOT |
| 16 JAN 2026 | 260116-G03 | Southwest | 200 | $67.26 | $80.06 | 2 | Capital Paving & Construction, LLC | MoDOT |
| 12 DEC 2025 | 251212-D02 | Central | 133 | $70.00 | $70.00 | 3 | Sam Gaines Construction, Inc. | MoDOT |
| 14 NOV 2025 | 251114-A02 | Northwest | 1 | $215.00 | $115.00 | 5 | Emery Sapp & Sons, Inc. | MoDOT |
| 14 NOV 2025 | 251114-G01 | Southwest | 11 | $108.15 | $109.37 | 4 | Blevins Asphalt Construction Company, Inc. | MoDOT |
| 17 OCT 2025 | 251017-B1A | Northeast | 6 | $337.96 | $337.96 | 3 | Magruder Paving, LLC | MoDOT |
| 17 OCT 2025 | 251017-D02 | Central | 30 | $100.00 | $90.50 | 2 | Capital Paving & Construction, LLC | MoDOT |
| 17 OCT 2025 | 251017-D02 | Central | 133 | $100.00 | $90.50 | 2 | Capital Paving & Construction, LLC | MoDOT |
| 19 SEP 2025 | 250919-F05 | St. Louis | 30 | $210.00 | $125.86 | 4 | N.B. West Contracting Company | MoDOT |
| 19 SEP 2025 | 250919-H02 | Southeast | 184 | $104.82 | $104.82 | 3 | Robertson Contractors, Inc. | MoDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.
How these prices were read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way