Low bidders on MoDOT contracts carried a median of $27.25 per LF for item 9031250A, u-channel post, 3 lb, over the 24 months to 16 OCT 2026, across 25 low bids. Half of all 80 bids fell between $20.00 and $34.00.

Owner
Missouri DOT
Item
9031250A
Unit
LF
Latest letting
16 OCT 2026
$27.25Low bidder's median, per LF
$26.29Median of all bids, per LF
24Contracts in the window

By year of letting

U-channel post, 3 lb, MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202099$15.0054$18.51
202199$22.2627$22.26
202289$26.0027$24.00
20231415$25.0049$25.00
20242325$25.0074$22.50
202577$24.0026$24.00
20261010$24.0931$28.62
U-channel post, 3 lb, MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

U-channel post, 3 lb, MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Central11$27.4536$26.00
Southeast3$24.0014$24.00
Southwest3$35.2511$31.00
Northwest5$23.8011$26.18
U-channel post, 3 lb, MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

U-channel post, 3 lb, MoDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
14 to 696$23.73
73 to 1276$28.66
138 to 1926$22.90
196 to 6447$27.25
U-channel post, 3 lb, MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying U-channel post, 3 lb
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
16 OCT 2026261016-D08Central336$34.00$34.003Pace Construction Company, LLCMoDOT
16 OCT 2026261016-D12Central56$20.00$34.003Pace Construction Company, LLCMoDOT
18 SEP 2026260918-D01Central464$17.40$16.003Emery Sapp & Sons, Inc.MoDOT
15 MAY 2026260515-D03Central73$32.00$32.344H.R. Quadri Contractors, LLCMoDOT
15 MAY 2026260515-G10Southwest96$28.70$31.003Hartman and Company, Inc.MoDOT
20 MAR 2026260320-B04Northeast127$24.37$24.371Louis-Company, LLCMoDOT
20 FEB 2026260220-A01Northwest119$28.62$31.812Louis-Company, LLCMoDOT
20 FEB 2026260220-A02Northwest138$16.50$27.234Decatur Bridge & Iron LLCMoDOT
16 JAN 2026260116-A01Northwest168$23.80$25.253Herzog Contracting Corp.MoDOT
16 JAN 2026260116-D02Central168$19.12$16.415Mera Excavating, LLCMoDOT
12 DEC 2025251212-D02Central14$20.00$20.003Sam Gaines Construction, Inc.MoDOT
16 MAY 2025250516-D03Central336$31.49$27.007Louis-Company, LLCMoDOT
18 APR 2025250418-H05Southeast60$18.00$24.005Robertson Contractors, Inc.MoDOT
14 MAR 2025250314-A02Northwest96$51.44$51.441Louis-Company, LLCMoDOT
14 MAR 2025250314-H02Southeast119$24.00$24.006Penzel Construction Company, Inc.MoDOT
Latest MoDOT contracts carrying U-channel post, 3 lb

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy