Mgs bridge approach transition section (extended curb) unit price, Missouri
Low bidders on MoDOT contracts carried a median of $3,891.50 per EACH for item 6061068, mgs bridge approach transition section (extended curb), over the 24 months to 16 OCT 2026, across 34 low bids. Half of all 91 bids fell between $3,600.00 and $4,200.00.
- Owner
- Missouri DOT
- Item
- 6061068
- Unit
- EACH
- Latest letting
- 16 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 16 | 17 | $3,000.00 | 63 | $3,000.00 |
| 2021 | 9 | 9 | $3,400.00 | 30 | $3,300.00 |
| 2022 | 13 | 15 | $4,200.00 | 34 | $4,150.00 |
| 2023 | 13 | 17 | $4,100.00 | 31 | $4,100.00 |
| 2024 | 15 | 17 | $3,700.00 | 55 | $3,700.00 |
| 2025 | 17 | 17 | $3,900.00 | 44 | $4,200.00 |
| 2026 | 7 | 8 | $4,250.78 | 20 | $4,250.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| St. Louis | 6 | $4,200.00 | 22 | $4,200.00 |
| Kansas City | 7 | $3,519.15 | 17 | $3,532.00 |
| Southwest | 6 | $3,745.25 | 16 | $3,917.75 |
| Northwest | 5 | $3,700.00 | 15 | $3,600.00 |
| Southeast | 3 | $4,200.00 | 9 | $4,200.00 |
| Central | 4 | $3,800.00 | 7 | $3,900.00 |
| Northeast | 3 | $4,022.00 | 5 | $4,027.39 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 8 | $4,200.00 |
| 2 to 4 | 9 | $4,000.00 |
| 4 to 4 | 8 | $3,950.00 |
| 7 to 16 | 9 | $3,579.88 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 16 OCT 2026 | 261016-G10 | Southwest | 4 | $4,458.88 | $4,300.00 | 3 | APAC-Central, Inc. | MoDOT |
| 15 MAY 2026 | 260515-C05 | Kansas City | 12 | $3,883.00 | $3,841.50 | 2 | Ideker, Inc. | MoDOT |
| 15 MAY 2026 | 260515-F01 | St. Louis | 1 | $6,325.00 | $6,325.00 | 3 | R. V. Wagner, Inc. | MoDOT |
| 17 APR 2026 | 260417-H03 | Southeast | 4 | $4,200.00 | $4,200.00 | 4 | Penzel Construction Company, Inc. | MoDOT |
| 20 MAR 2026 | 260320-C06 | Kansas City | 1 | $4,301.57 | $4,100.78 | 2 | Hawkins Construction Company dba Hopco Construction, Inc. | MoDOT |
| 20 MAR 2026 | 260320-D03 | Central | 1 | $4,400.00 | $4,500.00 | 2 | Don Schnieders Excavating Company, Inc. | MoDOT |
| 16 JAN 2026 | 260116-G03 | Southwest | 7 | $3,579.88 | $4,261.22 | 2 | Capital Paving & Construction, LLC | MoDOT |
| 16 JAN 2026 | 260116-G03 | Southwest | 8 | $3,510.67 | $4,178.84 | 2 | Capital Paving & Construction, LLC | MoDOT |
| 17 OCT 2025 | 251017-C06 | Kansas City | 9 | $3,532.00 | $3,532.00 | 2 | Ideker, Inc. | MoDOT |
| 17 OCT 2025 | 251017-D02 | Central | 14 | $3,500.00 | $3,850.00 | 2 | Capital Paving & Construction, LLC | MoDOT |
| 17 OCT 2025 | 251017-F05 | St. Louis | 3 | $4,200.00 | $4,200.00 | 5 | N.B. West Contracting Company | MoDOT |
| 17 OCT 2025 | 251017-G02 | Southwest | 4 | $3,835.50 | $3,680.00 | 3 | Emery Sapp & Sons, Inc. | MoDOT |
| 17 OCT 2025 | 251017-G04 | Southwest | 2 | $4,000.00 | $4,476.65 | 2 | Hartman and Company, Inc. | MoDOT |
| 19 SEP 2025 | 250919-A02 | Northwest | 2 | $3,568.00 | $3,568.00 | 4 | Herzog Contracting Corp. | MoDOT |
| 20 JUN 2025 | 250620-C09 | Kansas City | 1 | $3,493.00 | $4,201.64 | 3 | Pyramid Contractors, Inc. | MoDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.
How these prices were read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.