Mgs bridge approach transition section (regular/no curb) unit price, Missouri

Low bidders on MoDOT contracts carried a median of $4,000.00 per EACH for item 6061069, mgs bridge approach transition section (regular/no curb), over the 24 months to 16 OCT 2026, across 189 low bids. Half of all 693 bids fell between $3,791.92 and $4,275.80.

Owner
Missouri DOT
Item
6061069
Unit
EACH
Latest letting
16 OCT 2026
$4,000.00Low bidder's median, per EACH
$4,009.21Median of all bids, per EACH
163Contracts in the window

By year of letting

Mgs bridge approach transition section (regular/no curb), MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20207688$2,855.00327$2,899.00
20217084$3,325.00272$3,212.50
20226879$3,950.00213$4,000.00
202383105$3,944.00324$4,000.00
20248393$3,800.00327$3,960.00
202590106$4,000.00383$4,100.00
20264449$4,100.00190$4,100.00
Mgs bridge approach transition section (regular/no curb), MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Mgs bridge approach transition section (regular/no curb), MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Southeast47$4,200.00170$4,200.00
Central41$4,000.00138$4,000.00
Southwest28$3,960.00107$3,947.58
Kansas City34$3,799.50100$3,869.50
St. Louis21$4,200.0086$4,200.00
Northeast9$4,075.7156$4,000.00
Northwest9$3,500.0036$3,822.43
Mgs bridge approach transition section (regular/no curb), MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Mgs bridge approach transition section (regular/no curb), MoDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 447$4,200.00
4 to 447$4,159.49
4 to 847$4,000.00
8 to 5448$3,811.22
Mgs bridge approach transition section (regular/no curb), MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying Mgs bridge approach transition section (regular/no curb)
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
16 OCT 2026261016-D06Central4$4,000.00$4,000.005Gene Haile Excavating, Inc.MoDOT
16 OCT 2026261016-G01Southwest2$4,000.00$4,000.003APAC-Central, Inc.MoDOT
16 OCT 2026261016-G01Southwest4$4,000.00$4,000.003APAC-Central, Inc.MoDOT
16 OCT 2026261016-G07Southwest4$5,500.00$3,947.589Widel, Inc.MoDOT
16 OCT 2026261016-G12Southwest4$4,689.25$4,536.872KCI Construction CompanyMoDOT
18 SEP 2026260918-C04Kansas City4$4,347.00$4,347.003Amino Bros. Co., Inc.MoDOT
18 SEP 2026260918-D04Central11$2,753.28$3,025.003Capital Paving & Construction, LLCMoDOT
18 SEP 2026260918-D05Central4$4,700.00$3,973.732Christensen Construction Co.MoDOT
18 SEP 2026260918-F03St. Louis3$4,850.00$4,675.002Concrete Strategies, LLCMoDOT
18 SEP 2026260918-G02Southwest8$3,771.00$3,938.004APAC-Central, Inc.MoDOT
18 SEP 2026260918-H01Southeast4$4,500.00$4,500.001Pace Construction Company, LLCMoDOT
18 SEP 2026260918-H02Southeast36$5,135.00$4,986.262West Plains Bridge & Grading, LLCMoDOT
18 SEP 2026260918-H03Southeast67n/a$4,713.841West Plains Bridge & Grading, LLCMoDOT
18 JUN 2026260618-C02Kansas City6$4,786.56$4,250.004Louis-Company, LLCMoDOT
18 JUN 2026260618-F01St. Louis5$4,000.00$4,000.004Millstone Weber, LLCMoDOT
Latest MoDOT contracts carrying Mgs bridge approach transition section (regular/no curb)

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.