Placing rock fill unit price, Missouri

Low bidders on MoDOT contracts carried a median of $13.60 per CY for item 2143000, placing rock fill, over the 24 months to 16 OCT 2026, across 29 low bids. Half of all 136 bids fell between $11.88 and $29.99.

Owner
Missouri DOT
Item
2143000
Unit
CY
Latest letting
15 MAY 2026
$13.60Low bidder's median, per CY
$19.26Median of all bids, per CY
26Contracts in the window

By year of letting

Placing rock fill, MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202089$13.0037$19.00
20211517$25.0062$20.82
20221212$17.9550$17.95
20231313$20.4148$20.20
20241616$22.5073$21.70
20251417$13.6078$20.48
202688$13.0039$14.00
Placing rock fill, MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Placing rock fill, MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Northeast6$11.7541$18.00
Central9$20.0031$24.60
Southwest5$13.0023$16.40
St. Louis4$34.0018$33.00
Placing rock fill, MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Placing rock fill, MoDOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
89 to 2157$25.00
262 to 6357$25.00
1,190 to 3,5597$13.00
4,494 to 46,7078$7.25
Placing rock fill, MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying Placing rock fill
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
15 MAY 2026260515-D03Central209$20.00$20.004H.R. Quadri Contractors, LLCMoDOT
17 APR 2026260417-F05St. Louis10,834$10.73$22.007CSD Environmental Services, Inc.MoDOT
20 MAR 2026260320-D02Central118$25.00$25.003E & C Bridge, LLCMoDOT
20 MAR 2026260320-D03Central5,689$8.00$6.122Don Schnieders Excavating Company, Inc.MoDOT
16 JAN 2026260116-C04Kansas City46,707$5.40$5.3510Magruder Construction Co., Inc.MoDOT
16 JAN 2026260116-F01St. Louis415$35.00$37.502Pace Construction Company, LLCMoDOT
16 JAN 2026260116-F08St. Louis4,410n/a$20.001MoDOT
16 JAN 2026260116-G04Southwest1,211$13.00$13.005Robertson Contractors, Inc.MoDOT
16 JAN 2026260116-G04Southwest390$13.00$17.215Robertson Contractors, Inc.MoDOT
12 DEC 2025251212-B03Northeast2,154$10.00$15.005Magruder Construction Co., Inc.MoDOT
12 DEC 2025251212-D03Central156$25.00$26.256E & C Bridge, LLCMoDOT
12 DEC 2025251212-D04Central366$25.00$25.007E & C Bridge, LLCMoDOT
14 NOV 2025251114-D01Central26,782$12.00$12.001Emery Sapp & Sons, Inc.MoDOT
14 NOV 2025251114-D01Central3,559$13.00$13.001Emery Sapp & Sons, Inc.MoDOT
14 NOV 2025251114-F03St. Louis2,534$33.00$33.004N.B. West Contracting CompanyMoDOT
Latest MoDOT contracts carrying Placing rock fill

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.