Subgrade compaction (6-inch depth) unit price, Missouri
Low bidders on MoDOT contracts carried a median of $1,166.59 per 100F for item 2101006A, subgrade compaction (6-inch depth), over the 24 months to 16 OCT 2026, across 44 low bids. Half of all 174 bids fell between $715.00 and $1,737.50.
- Owner
- Missouri DOT
- Item
- 2101006A
- Unit
- 100F
- Latest letting
- 18 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 9 | 12 | $485.93 | 49 | $527.75 |
| 2021 | 19 | 22 | $675.00 | 88 | $775.00 |
| 2022 | 10 | 10 | $1,016.00 | 28 | $1,233.11 |
| 2023 | 21 | 25 | $850.00 | 87 | $1,000.00 |
| 2024 | 23 | 27 | $1,233.18 | 123 | $1,132.00 |
| 2025 | 21 | 28 | $1,179.09 | 104 | $1,348.50 |
| 2026 | 7 | 7 | $1,000.00 | 26 | $910.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Northeast | 12 | $1,200.00 | 62 | $1,405.00 |
| Kansas City | 15 | $1,297.00 | 42 | $1,323.50 |
| Southwest | 7 | $1,100.00 | 30 | $1,215.88 |
| Southeast | 5 | $1,100.00 | 20 | $810.00 |
| Northwest | 3 | $3,000.00 | 13 | $1,132.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (100F) | Low bids | Low-bid median |
|---|---|---|
| 1 to 3 | 11 | $1,425.00 |
| 3 to 5 | 11 | $1,297.00 |
| 5 to 8 | 11 | $1,400.00 |
| 9 to 227 | 11 | $750.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 JUN 2026 | 260618-H01 | Southeast | 8 | $315.00 | $810.00 | 4 | Robertson Contractors, Inc. | MoDOT |
| 15 MAY 2026 | 260515-C13 | Kansas City | 5 | $1,800.00 | $1,501.67 | 3 | E & C Bridge, LLC | MoDOT |
| 15 MAY 2026 | 260515-F01 | St. Louis | 4 | $565.00 | $565.00 | 3 | R. V. Wagner, Inc. | MoDOT |
| 15 MAY 2026 | 260515-H02 | Southeast | 9.10 | $1,100.00 | $1,305.00 | 4 | Fronabarger Concreters, Inc. | MoDOT |
| 20 FEB 2026 | 260220-G01 | Southwest | 37.80 | $347.50 | $201.25 | 2 | Hartman and Company, Inc. | MoDOT |
| 16 JAN 2026 | 260116-C03 | Kansas City | 7 | $1,000.00 | $1,653.50 | 4 | T&B Trucking and Excavating, LLC | MoDOT |
| 16 JAN 2026 | 260116-H03 | Southeast | 4 | $2,360.00 | $637.50 | 6 | PCX Construction, LLC | MoDOT |
| 12 DEC 2025 | 251212-B03 | Northeast | 4 | $970.00 | $1,450.00 | 5 | Magruder Construction Co., Inc. | MoDOT |
| 14 NOV 2025 | 251114-C06 | Kansas City | 3 | $2,281.00 | $2,286.65 | 6 | Epic Concrete Construction, Inc. | MoDOT |
| 14 NOV 2025 | 251114-C11 | Kansas City | 5 | $2,823.30 | $2,403.73 | 2 | Clarkson Construction Company | MoDOT |
| 19 SEP 2025 | 250919-B02 | Northeast | 5 | $1,400.00 | $1,300.00 | 4 | Bleigh Construction Company | MoDOT |
| 19 SEP 2025 | 250919-B02 | Northeast | 1 | $1,600.00 | $2,025.00 | 4 | Bleigh Construction Company | MoDOT |
| 19 SEP 2025 | 250919-H01 | Southeast | 13 | $335.00 | $600.00 | 3 | Robertson Contractors, Inc. | MoDOT |
| 15 AUG 2025 | 250815-G03 | Southwest | 1 | $1,425.00 | $1,975.47 | 6 | West Plains Bridge & Grading, LLC | MoDOT |
| 15 AUG 2025 | 250815-G03 | Southwest | 2 | $1,100.00 | $1,165.88 | 6 | West Plains Bridge & Grading, LLC | MoDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.
How these prices were read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.