Porous backfill unit price, Missouri

Low bidders on MoDOT contracts carried a median of $115.00 per CY for item 2064000, porous backfill, over the 24 months to 16 OCT 2026, across 27 low bids. Half of all 105 bids fell between $85.00 and $136.00.

Owner
Missouri DOT
Item
2064000
Unit
CY
Latest letting
18 JUN 2026
$115.00Low bidder's median, per CY
$110.00Median of all bids, per CY
20Contracts in the window

By year of letting

Porous backfill, MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
2020914$68.0062$80.00
202144$80.0011$82.00
202266$100.0015$100.00
202333$120.008$76.88
20241218$95.0069$95.00
20251218$122.5066$122.50
202678$85.5035$91.00
Porous backfill, MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Porous backfill, MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Southeast24$115.00101$110.00
Kansas City3$217.754$217.93
Porous backfill, MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Porous backfill, MoDOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
13 to 376$135.00
39 to 537$110.00
54 to 637$115.00
67 to 4547$115.00
Porous backfill, MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying Porous backfill
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 JUN 2026260618-H01Southeast171$120.00$106.004Robertson Contractors, Inc.MoDOT
18 JUN 2026260618-H03Southeast68$115.00$98.506Robertson Contractors, Inc.MoDOT
15 MAY 2026260515-H03Southeast83$81.00$80.504Penzel Construction Company, Inc.MoDOT
15 MAY 2026260515-H03Southeast53$76.00$95.504Penzel Construction Company, Inc.MoDOT
15 MAY 2026260515-H08Southeast57$135.00$102.502Robertson Contractors, Inc.MoDOT
17 APR 2026260417-H03Southeast49$88.00$111.504Penzel Construction Company, Inc.MoDOT
16 JAN 2026260116-H02Southeast454$62.00$85.005Robertson Contractors, Inc.MoDOT
16 JAN 2026260116-H03Southeast71$83.00$81.506PCX Construction, LLCMoDOT
12 DEC 2025251212-C02Kansas City103$150.88$150.881Clarkson Construction CompanyMoDOT
12 DEC 2025251212-H03Southeast63$120.00$97.005Robertson Contractors, Inc.MoDOT
12 DEC 2025251212-H03Southeast45$127.00$90.005Robertson Contractors, Inc.MoDOT
12 DEC 2025251212-H04Southeast54$115.00$115.003Joe's Bridge & Grading, Inc.MoDOT
14 NOV 2025251114-H05Southeast53$85.00$82.007Joe's Bridge & Grading, Inc.MoDOT
17 OCT 2025251017-H01Southeast54$115.00$126.922Joe's Bridge & Grading, Inc.MoDOT
19 SEP 2025250919-H03Southeast54$115.00$117.508Gene Haile Excavating, Inc.MoDOT
Latest MoDOT contracts carrying Porous backfill

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy