Shear connectors unit price, Missouri

Low bidders on MoDOT contracts carried a median of $12.00 per EACH for item 7121159, shear connectors, over the 24 months to 16 OCT 2026, across 27 low bids. Half of all 97 bids fell between $9.00 and $15.50.

Owner
Missouri DOT
Item
7121159
Unit
EACH
Latest letting
18 JUN 2026
$12.00Low bidder's median, per EACH
$12.00Median of all bids, per EACH
18Contracts in the window

By year of letting

Shear connectors, MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202012$8.254$12.75
2021610$9.4531$8.00
20221112$11.2848$10.62
202379$11.0029$11.50
202467$7.7523$8.00
20251017$12.8567$12.80
202667$11.2224$11.36
Shear connectors, MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Shear connectors, MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Northwest11$12.0037$11.50
Central7$11.2232$13.00
Southeast4$9.5013$10.00
Kansas City3$5.177$12.50
Shear connectors, MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Shear connectors, MoDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
144 to 7446$32.50
840 to 1,6327$14.00
1,656 to 2,5207$8.50
2,560 to 3,4447$8.98
Shear connectors, MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying Shear connectors
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 JUN 2026260618-H01Southeast2,232$7.00$7.504Robertson Contractors, Inc.MoDOT
15 MAY 2026260515-H08Southeast1,320$11.50$10.752Robertson Contractors, Inc.MoDOT
20 MAR 2026260320-D01Central2,520$11.22$9.364Louis-Company, LLCMoDOT
20 MAR 2026260320-D01Central2,976$8.98$8.244Louis-Company, LLCMoDOT
20 MAR 2026260320-D02Central384$20.00$20.003E & C Bridge, LLCMoDOT
16 JAN 2026260116-D01Central208$15.00$37.005Gene Haile Excavating, Inc.MoDOT
16 JAN 2026260116-D04Central2,574$9.90$11.952West Plains Bridge & Grading, LLCMoDOT
12 DEC 2025251212-A02Northwest1,512$15.00$14.432E & C Bridge, LLCMoDOT
12 DEC 2025251212-A02Northwest1,056$15.00$15.452E & C Bridge, LLCMoDOT
12 DEC 2025251212-A02Northwest2,808$12.00$12.582E & C Bridge, LLCMoDOT
12 DEC 2025251212-D04Central856$14.00$15.957E & C Bridge, LLCMoDOT
12 DEC 2025251212-H03Southeast160$45.00$22.755Robertson Contractors, Inc.MoDOT
14 NOV 2025251114-F08St. Louis144$49.00$52.504Kozeny-Wagner, Inc.MoDOT
14 NOV 2025251114-F08St. Louis144$49.00$52.504Kozeny-Wagner, Inc.MoDOT
19 SEP 2025250919-A01Northwest1,656$12.85$13.432Louis-Company, LLCMoDOT
Latest MoDOT contracts carrying Shear connectors

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy