Slab drain unit price, Missouri

Low bidders on MoDOT contracts carried a median of $490.54 per EACH for item 7123610, slab drain, over the 24 months to 16 OCT 2026, across 128 low bids. Half of all 490 bids fell between $440.39 and $650.00.

Owner
Missouri DOT
Item
7123610
Unit
EACH
Latest letting
16 OCT 2026
$490.54Low bidder's median, per EACH
$545.00Median of all bids, per EACH
84Contracts in the window

By year of letting

Slab drain, MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20203851$325.00227$350.00
20212850$477.50183$465.00
20222733$450.00119$525.00
20233747$500.00187$540.00
20244158$480.00245$516.00
20254974$450.00286$503.00
20262738$590.04150$575.00
Slab drain, MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Slab drain, MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Southeast30$457.50129$495.00
Central27$394.38128$513.50
Northwest27$444.1773$500.00
Southwest12$600.0051$552.00
Northeast9$430.0046$550.00
Kansas City17$896.5841$660.00
St. Louis6$890.0022$788.50
Slab drain, MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Slab drain, MoDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 1432$600.00
14 to 2032$450.00
20 to 3232$473.04
32 to 8432$447.09
Slab drain, MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying Slab drain
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
16 OCT 2026261016-G07Southwest4$575.00$575.009Widel, Inc.MoDOT
18 JUN 2026260618-F01St. Louis1$930.00$901.004Millstone Weber, LLCMoDOT
18 JUN 2026260618-F01St. Louis9$1,051.00$796.504Millstone Weber, LLCMoDOT
18 JUN 2026260618-F01St. Louis9$1,051.00$795.004Millstone Weber, LLCMoDOT
18 JUN 2026260618-H01Southeast48$480.00$517.994Robertson Contractors, Inc.MoDOT
18 JUN 2026260618-H03Southeast32$550.00$564.506Robertson Contractors, Inc.MoDOT
15 MAY 2026260515-C13Kansas City32$500.00$596.743E & C Bridge, LLCMoDOT
15 MAY 2026260515-D03Central11$680.00$666.764H.R. Quadri Contractors, LLCMoDOT
15 MAY 2026260515-D05Central18$550.00$646.005Robertson Contractors, Inc.MoDOT
15 MAY 2026260515-G08Southwest20$643.00$643.005Hartman and Company, Inc.MoDOT
15 MAY 2026260515-G09Southwest26$700.00$561.005Emery Sapp & Sons, Inc.MoDOT
15 MAY 2026260515-G10Southwest10$552.00$710.003Hartman and Company, Inc.MoDOT
15 MAY 2026260515-H03Southeast24$703.00$661.504Penzel Construction Company, Inc.MoDOT
15 MAY 2026260515-H03Southeast10$655.00$622.004Penzel Construction Company, Inc.MoDOT
15 MAY 2026260515-H08Southeast16$600.00$587.502Robertson Contractors, Inc.MoDOT
Latest MoDOT contracts carrying Slab drain

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy