Approach guide rail transition tl-3 unit price, New Jersey

Low bidders on NJDOT contracts carried a median of $4,717.50 per U for item 609059M, approach guide rail transition tl-3, over the 24 months to 16 APR 2026, across 16 low bids. Half of all 67 bids fell between $4,492.50 and $5,395.07.

Owner
New Jersey DOT
Item
609059M
Unit
U
Latest letting
18 NOV 2025
$4,717.50Low bidder's median, per U
$4,900.00Median of all bids, per U
16Contracts in the window

By year of letting

Approach guide rail transition tl-3, NJDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20181818$3,400.00103$3,500.00
20192323$3,500.00116$3,739.36
20201111$3,520.0069$3,700.00
202177$4,728.0041$4,900.00
20221010$3,817.5031$5,200.00
20231111$4,540.0044$4,500.00
202488$3,900.0025$4,500.00
202599$5,000.0045$4,950.00
Approach guide rail transition tl-3, NJDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Approach guide rail transition tl-3, NJDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
N15$5,490.1530$5,000.00
S18$4,000.0021$4,500.00
C13$4,300.0016$4,942.50
Approach guide rail transition tl-3, NJDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Approach guide rail transition tl-3, NJDOT: low bidder's median by quantity band
Quantity (U)Low bidsLow-bid median
1 to 24$5,495.07
2 to 64$4,750.00
6 to 124$3,750.00
14 to 254$4,467.50
Approach guide rail transition tl-3, NJDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NJDOT contracts carrying Approach guide rail transition tl-3
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 NOV 202525128N11$5,490.15$4,900.007IEW CONSTRUCTION GROUP, INC.NJDOT
30 OCT 202525130N12$5,000.00$4,950.004UNION PAVING & CONSTRUCTION CO., INC.NJDOT
23 OCT 202525133N16$5,000.00$5,500.002RITACCO CONSTRUCTION, INC.NJDOT
23 OCT 202525136S117$4,000.00$4,441.253SOUTH STATE, INC.NJDOT
19 JUN 202525112C119$4,935.00$4,917.506DELLA PELLO PAVING, INC.NJDOT
29 MAY 202525108C12$4,300.00$4,952.358RITACCO CONSTRUCTION, INC.NJDOT
01 MAY 202525102N12$8,000.00$6,250.0010SPARWICK CONTRACTING, INC.NJDOT
03 APR 202525103S13$5,200.00$5,000.003MIDLANTIC CONSTRUCTION, LLCNJDOT
14 JAN 202524152C18$3,700.00$4,350.002SOUTH STATE, INC.NJDOT
24 OCT 202424148S125$4,941.00$4,941.003RICHARD E. PIERSON CONSTRUCTION CO., INC.NJDOT
17 OCT 202424144N12$5,500.00$4,825.007FERREIRA CONSTRUCTION CO., INC.NJDOT
26 SEP 202424132S16$4,500.00$5,000.004RICHARD E. PIERSON CONSTRUCTION CO., INC.NJDOT
27 AUG 202424128S18$3,800.00$3,800.001SOUTH STATE, INC.NJDOT
06 JUN 202424120S114$4,000.00$3,850.002CREAMER RUBERTON, A JOINT VENTURENJDOT
06 JUN 202424122S12$3,700.00$4,930.912SOUTH STATE, INC.NJDOT
Latest NJDOT contracts carrying Approach guide rail transition tl-3

Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.

How these prices were read

NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy