Removal of beam guide rail unit price, New Jersey

Low bidders on NJDOT contracts carried a median of $1.00 per LF for item 609075M, removal of beam guide rail, over the 24 months to 16 APR 2026, across 39 low bids. Half of all 186 bids fell between $1.00 and $4.00.

Owner
New Jersey DOT
Item
609075M
Unit
LF
Latest letting
19 FEB 2026
$1.00Low bidder's median, per LF
$1.18Median of all bids, per LF
40Contracts in the window

By year of letting

Removal of beam guide rail, NJDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20171616$1.0997$1.10
20182829$1.00151$1.20
20193428$1.50158$3.00
20202018$2.12132$3.00
20212828$2.00141$3.00
20222828$2.5095$3.25
20232624$2.2587$2.23
20241920$1.0081$1.30
20252119$1.00102$1.15
202622$2.5013$4.00
Removal of beam guide rail, NJDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Removal of beam guide rail, NJDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
N113$1.1671$1.30
C110$1.0065$2.00
S113$1.0037$1.00
Removal of beam guide rail, NJDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Removal of beam guide rail, NJDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
92 to 4339$1.08
470 to 1,28810$1.00
1,748 to 4,00010$1.00
4,273 to 74,96910$1.00
Removal of beam guide rail, NJDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NJDOT contracts carrying Removal of beam guide rail
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
19 FEB 202624474H41,748$1.00$3.004BERTO CONSTRUCTION, INC.NJDOT
12 FEB 202625139C1433$4.00$4.009MIDLANTIC CONSTRUCTION, LLCNJDOT
25 NOV 202525603S12,330$1.00$1.002ORCHARD HOLDINGS, LLCNJDOT
18 NOV 202525128N14,000$1.16$3.007IEW CONSTRUCTION GROUP, INC.NJDOT
30 OCT 202525130N15,684$4.00$1.104UNION PAVING & CONSTRUCTION CO., INC.NJDOT
30 OCT 202525601N1976n/a$1.003DAIDONE ELECTRIC, INC.NJDOT
23 OCT 202525133N13,305$1.00$1.502RITACCO CONSTRUCTION, INC.NJDOT
23 OCT 202525134C1600n/a$2.004EARLE ASPHALT COMPANYNJDOT
23 OCT 202525136S115,279$1.00$1.003SOUTH STATE, INC.NJDOT
23 OCT 202525602N1325$1.00$1.005DAIDONE ELECTRIC, INC.NJDOT
07 OCT 202525126C1830$2.00$3.504NEW PRINCE CONCRETE CONSTRUCTION CO., INC.NJDOT
26 AUG 202525122C13,884$1.00$1.0010PKF-MARK III, INC.NJDOT
12 AUG 202525121N11,167$10.00$1.074JOSEPH M. SANZARI, INC.NJDOT
19 JUN 202525112C174,969$1.20$1.626DELLA PELLO PAVING, INC.NJDOT
05 JUN 202525111S1422$1.00$1.003SOUTH STATE, INC.NJDOT
Latest NJDOT contracts carrying Removal of beam guide rail

Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.

How these prices were read

NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy