Crew coordinator unit price, New Jersey

Low bidders on NJDOT contracts carried a median of $125.00 per HR for item MMB092M, crew coordinator, over the 24 months to 16 APR 2026, across 40 low bids. Half of all 111 bids fell between $112.50 and $135.00.

Owner
New Jersey DOT
Item
MMB092M
Unit
HR
Latest letting
14 APR 2026
$125.00Low bidder's median, per HR
$130.00Median of all bids, per HR
40Contracts in the window

By year of letting

Crew coordinator, NJDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20181616$135.0057$135.00
20191212$145.5039$145.00
20201111$125.0045$125.00
20211717$125.0051$125.00
20221717$140.0057$140.00
20231717$140.0049$140.00
20241919$120.0050$120.00
20251717$125.0050$130.00
202644$125.0011$130.00
Crew coordinator, NJDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Crew coordinator, NJDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
C412$132.5047$135.00
N412$125.0032$125.00
S412$127.5028$130.00
H44$105.004$105.00
Crew coordinator, NJDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Crew coordinator, NJDOT: low bidder's median by quantity band
Quantity (HR)Low bidsLow-bid median
50 to 9010$135.00
100 to 15010$122.50
150 to 75010$130.00
1,000 to 4,22410$122.50
Crew coordinator, NJDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NJDOT contracts carrying Crew coordinator
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
14 APR 202626424H42,268$105.00$105.001IEW CONSTRUCTION GROUP, INC.NJDOT
26 MAR 202626439S4100$130.00$130.003IEW CONSTRUCTION GROUP, INC.NJDOT
24 MAR 202626438C4100$130.00$130.004COLONNELLI BROTHERS, INC.NJDOT
19 MAR 202626437N4200$120.00$120.003SPARWICK CONTRACTING, INC.NJDOT
23 DEC 202526433S4100$125.00$125.002COLONNELLI BROTHERS, INC.NJDOT
18 DEC 202526432C4100$125.00$125.004SPARWICK CONTRACTING, INC.NJDOT
16 DEC 202526431N4500$125.00$125.003IEW CONSTRUCTION GROUP, INC.NJDOT
18 NOV 202526436S4100$100.00$100.002IEW CONSTRUCTION GROUP, INC.NJDOT
13 NOV 202526435C4100$100.00$100.003IEW CONSTRUCTION GROUP, INC.NJDOT
06 NOV 202526434N41,000$125.00$125.002IEW CONSTRUCTION GROUP, INC.NJDOT
28 OCT 202526429C450$135.00$135.003IEW CONSTRUCTION GROUP, INC.NJDOT
23 OCT 202526430S450$135.00$135.002IEW CONSTRUCTION GROUP, INC.NJDOT
16 OCT 202526427S450$125.00$125.002DIACO CONTRACTING, INC. DBA GRADE CONSTRUCTIONNJDOT
16 OCT 202526428N41,500$130.00$130.003IEW CONSTRUCTION GROUP, INC.NJDOT
14 OCT 202526426C4500$135.00$135.004DIACO CONTRACTING, INC. DBA GRADE CONSTRUCTIONNJDOT
Latest NJDOT contracts carrying Crew coordinator

Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.

How these prices were read

NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy