Lane closures unit price, New Jersey

Low bidders on NJDOT contracts carried a median of $150.00 per HR for item MMB172M, lane closures, over the 24 months to 16 APR 2026, across 31 low bids. Half of all 89 bids fell between $1.00 and $225.00.

Owner
New Jersey DOT
Item
MMB172M
Unit
HR
Latest letting
14 APR 2026
$150.00Low bidder's median, per HR
$60.00Median of all bids, per HR
39Contracts in the window

By year of letting

Lane closures, NJDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20182318$24.5062$40.00
2019125$1.0029$1.00
2020146$106.3038$8.50
20212212$153.5042$132.50
20221711$157.0135$32.00
2023114$129.1222$1.00
20242015$65.0041$47.00
20251512$208.5037$50.00
202644$425.0011$298.00
Lane closures, NJDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Lane closures, NJDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
C49$150.0033$47.00
N48$125.0027$64.97
S49$50.0022$100.00
H45$496.007$496.00
Lane closures, NJDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Lane closures, NJDOT: low bidder's median by quantity band
Quantity (HR)Low bidsLow-bid median
750 to 9607$50.00
1,000 to 2,7008$195.00
3,225 to 4,3008$162.50
4,860 to 14,0008$193.50
Lane closures, NJDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NJDOT contracts carrying Lane closures
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
14 APR 202626424H44,860$558.13$558.131IEW CONSTRUCTION GROUP, INC.NJDOT
26 MAR 202626439S44,200$100.00$250.003IEW CONSTRUCTION GROUP, INC.NJDOT
24 MAR 202626438C42,500$400.00$192.504COLONNELLI BROTHERS, INC.NJDOT
19 MAR 202626437N43,225$450.00$307.003SPARWICK CONTRACTING, INC.NJDOT
23 DEC 202526433S43,550$225.00$192.492COLONNELLI BROTHERS, INC.NJDOT
18 DEC 202526432C44,000$230.00$29.983SPARWICK CONTRACTING, INC.NJDOT
16 DEC 202526431N44,000$64.97$64.973IEW CONSTRUCTION GROUP, INC.NJDOT
09 DEC 202526463H4960$1.00$50.003SPARWICK CONTRACTING, INC.NJDOT
28 OCT 202526429C44,010n/a$50.001IEW CONSTRUCTION GROUP, INC.NJDOT
23 OCT 202526430S41,500$49.75$115.882IEW CONSTRUCTION GROUP, INC.NJDOT
16 OCT 202526427S42,500$192.00$192.001DIACO CONTRACTING, INC. DBA GRADE CONSTRUCTIONNJDOT
16 OCT 202526428N44,000n/a$50.002IEW CONSTRUCTION GROUP, INC.NJDOT
14 OCT 202526426C47,000$150.00$75.502DIACO CONTRACTING, INC. DBA GRADE CONSTRUCTIONNJDOT
09 OCT 202526425N410,000n/a$169.002IEW CONSTRUCTION GROUP, INC.NJDOT
12 JUN 202525424H46,300$534.09$534.091IEW CONSTRUCTION GROUP, INC.NJDOT
Latest NJDOT contracts carrying Lane closures

Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.

How these prices were read

NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy