Asphalt curing seal unit price, North Carolina

Low bidders on NCDOT contracts carried a median of $5.75 per GAL for item 1209000000-E, asphalt curing seal, over the 24 months to 20 OCT 2026, across 3 low bids. Half of all 18 bids fell between $3.77 and $5.09.

Owner
North Carolina DOT
Item
1209000000-E
Unit
GAL
Latest letting
20 JAN 2026
$5.75Low bidder's median, per GAL
$4.80Median of all bids, per GAL
3Contracts in the window

By year of letting

Asphalt curing seal, NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201366$3.5035$3.50
201455$3.0045$2.90
201577$4.0048$4.00
201644$3.6826$3.75
201744$3.1237$3.25
201866$2.7033$3.05
201933$3.2414$3.29
202011$3.004$3.06
202133$2.7522$3.44
202411$4.805$4.85
202522$5.8813$5.00
202611$4.035$3.55
Asphalt curing seal, NCDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Asphalt curing seal, NCDOT: unit prices by county, all lettings
CountyLow bidsLow-bid medianAll bidsMedian, all bids
Guilford6$3.1242$3.06
Forsyth3$3.2528$3.12
Wake3$2.7522$3.65
Cabarrus3$3.3219$3.46
Mecklenburg3$4.0010$4.25
Asphalt curing seal, NCDOT: unit prices by county, all lettings

Countys with at least three low bids, over all lettings.

By quantity

Asphalt curing seal, NCDOT: low bidder's median by quantity band
Quantity (GAL)Low bidsLow-bid median
70 to 5,90010$4.00
6,780 to 15,33011$3.32
19,350 to 26,55011$3.10
31,360 to 84,04011$2.90
Asphalt curing seal, NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NCDOT contracts carrying Asphalt curing seal
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
20 JAN 2026C205117Cabarrus2,350$4.03$3.555NJR GROUP INCNCDOT
21 OCT 2025C205093Davie7,190$5.75$5.0010BRANCH CIVIL INCNCDOT
16 SEP 2025C204971Guilford23,290$6.00$6.233BLYTHE CONSTRUCTION INCNCDOT
15 OCT 2024C204348Iredell, Catawba19,980$4.80$4.855BLYTHE DEVELOPMENT LLCNCDOT
21 DEC 2021C204397Rutherford55,490$2.75$2.882WRIGHT BROTHERS CONSTRUCTION COMPANY INCNCDOT
19 OCT 2021C204399Davidson4,960$3.44$3.4412SMITH-ROWE, LLCNCDOT
20 APR 2021C204499Guilford14,400$2.50$4.128APAC - ATLANTIC INC THOMPSON ARTHUR DIVISIONNCDOT
17 MAR 2020C204356Ashe13,950$3.00$3.064JAMES R VANNOY & SONS CONSTRUCTION COMPANY INCNCDOT
19 NOV 2019C204351Wake4,200$2.71$3.256ZACHRY CONSTRUCTION CORPORATIONNCDOT
15 OCT 2019C204368Richmond84,040$3.24$3.055SHARPE BROTHERS A DIV OF VECELLIO & GROGAN INCNCDOT
15 OCT 2019C204181Stanly, Montgomery35,430$3.35$3.403BLYTHE DEVELOPMENT CONCDOT
02 OCT 2018C204108Johnston19,590$2.65$2.503W C ENGLISH INCORPORATEDNCDOT
17 JUL 2018C204105Franklin, Wake34,310$2.65$2.755FSC II LLC DBA FRED SMITH COMPANYNCDOT
17 JUL 2018C204106Alamance4,970$3.10$3.588THALLE CONSTRUCTION CO., INC.NCDOT
19 JUN 2018C204103Guilford25,200$3.33$3.057BRANCH CIVIL INCNCDOT
Latest NCDOT contracts carrying Asphalt curing seal

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy