Pc for soil cement base unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $268.95 per TON for item 1187000000-E, pc for soil cement base, over the 24 months to 20 OCT 2026, across 5 low bids. Half of all 42 bids fell between $253.00 and $285.00.
- Owner
- North Carolina DOT
- Item
- 1187000000-E
- Unit
- TON
- Latest letting
- 20 JAN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 7 | 7 | $145.00 | 41 | $145.00 |
| 2014 | 5 | 5 | $136.50 | 45 | $136.50 |
| 2015 | 10 | 10 | $148.00 | 60 | $152.50 |
| 2016 | 11 | 11 | $169.00 | 52 | $170.97 |
| 2017 | 7 | 7 | $170.56 | 42 | $176.41 |
| 2018 | 9 | 9 | $190.00 | 46 | $183.32 |
| 2019 | 6 | 6 | $189.00 | 22 | $193.00 |
| 2020 | 2 | 2 | $195.25 | 9 | $198.00 |
| 2021 | 6 | 6 | $194.91 | 27 | $191.75 |
| 2022 | 1 | 1 | $214.00 | 3 | $214.00 |
| 2023 | 2 | 2 | $276.50 | 12 | $280.12 |
| 2024 | 4 | 4 | $273.00 | 21 | $287.25 |
| 2025 | 4 | 4 | $260.98 | 37 | $263.00 |
| 2026 | 1 | 1 | $309.41 | 5 | $269.05 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Guilford | 6 | $181.88 | 42 | $175.00 |
| Cabarrus | 7 | $190.00 | 39 | $190.00 |
| Mecklenburg | 9 | $190.50 | 37 | $190.50 |
| Forsyth | 4 | $169.78 | 36 | $172.78 |
| Chatham | 3 | $253.00 | 32 | $264.49 |
| Alamance | 3 | $175.00 | 24 | $181.98 |
| Union | 7 | $155.00 | 21 | $156.50 |
| Ashe | 3 | $185.00 | 19 | $180.00 |
| Cleveland | 3 | $170.14 | 18 | $151.00 |
| Anson | 4 | $151.51 | 14 | $151.51 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 78 to 617 | 18 | $190.00 |
| 621 to 1,480 | 19 | $180.00 |
| 1,493 to 2,810 | 19 | $170.56 |
| 2,875 to 9,358 | 19 | $152.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 JAN 2026 | C205117 | Cabarrus | 219 | $309.41 | $269.05 | 5 | NJR GROUP INC | NCDOT |
| 21 OCT 2025 | C205093 | Davie | 671 | $308.00 | $267.00 | 10 | BRANCH CIVIL INC | NCDOT |
| 16 SEP 2025 | C204971 | Guilford | 2,180 | $268.95 | $304.65 | 3 | BLYTHE CONSTRUCTION INC | NCDOT |
| 20 MAY 2025 | C205032 | Chatham | 1,600 | $253.00 | $253.00 | 12 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 18 MAR 2025 | C204933 | Chatham | 590 | $232.00 | $251.90 | 12 | BARNHILL CONTRACTING CO | NCDOT |
| 15 OCT 2024 | C204348 | Iredell, Catawba | 1,865 | $295.00 | $271.00 | 5 | BLYTHE DEVELOPMENT LLC | NCDOT |
| 16 JUL 2024 | C204843 | Randolph | 1,522 | $251.00 | $291.01 | 4 | CONTI CIVIL LLC | NCDOT |
| 18 JUN 2024 | C204951 | Hoke, Cumberland | 9,358 | $208.00 | $211.00 | 3 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 18 JUN 2024 | C204501 | Mecklenburg | 241 | $300.00 | $300.00 | 9 | SEALAND CONTRACTORS CORP | NCDOT |
| 15 AUG 2023 | C204872 | Chatham | 900 | $278.00 | $280.12 | 8 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 18 JUL 2023 | C204851 | Cleveland | 4,320 | $275.00 | $284.06 | 4 | AMES CONSTRUCTION INC | NCDOT |
| 15 MAR 2022 | C204704 | Mecklenburg | 1,411 | $214.00 | $214.00 | 3 | BLYTHE BROTHERS ASPHALT CO LLC | NCDOT |
| 21 DEC 2021 | C204397 | Rutherford | 5,179 | $240.00 | $240.00 | 2 | WRIGHT BROTHERS CONSTRUCTION COMPANY INC | NCDOT |
| 21 DEC 2021 | C204686 | Cabarrus | 1,597 | $210.00 | $191.03 | 6 | NJR GROUP INC | NCDOT |
| 15 JUN 2021 | C204646 | Mecklenburg | 283 | $198.06 | $186.88 | 4 | BOGGS CONTRACTING INC | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way