Drainage ditch excavation unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $22.98 per CY for item 0134000000-E, drainage ditch excavation, over the 24 months to 20 OCT 2026, across 96 low bids. Half of all 509 bids fell between $15.00 and $35.00.
- Owner
- North Carolina DOT
- Item
- 0134000000-E
- Unit
- CY
- Latest letting
- 20 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 62 | 62 | $10.00 | 331 | $9.00 |
| 2014 | 40 | 40 | $6.58 | 244 | $7.00 |
| 2015 | 35 | 35 | $7.00 | 221 | $8.00 |
| 2016 | 32 | 32 | $10.00 | 173 | $10.00 |
| 2017 | 26 | 26 | $8.00 | 152 | $10.00 |
| 2018 | 42 | 42 | $14.25 | 189 | $12.00 |
| 2019 | 23 | 23 | $12.00 | 109 | $12.00 |
| 2020 | 9 | 9 | $17.43 | 50 | $15.00 |
| 2021 | 34 | 34 | $11.66 | 167 | $15.00 |
| 2022 | 43 | 43 | $17.50 | 190 | $16.88 |
| 2023 | 35 | 35 | $25.00 | 166 | $24.55 |
| 2024 | 36 | 35 | $25.00 | 193 | $24.00 |
| 2025 | 51 | 50 | $18.50 | 264 | $20.48 |
| 2026 | 36 | 36 | $24.21 | 190 | $25.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Wake | 6 | $36.75 | 38 | $25.87 |
| Mecklenburg | 5 | $21.00 | 37 | $25.00 |
| Forsyth | 6 | $17.29 | 35 | $19.30 |
| Guilford | 5 | $15.00 | 25 | $22.15 |
| Rockingham | 5 | $22.45 | 23 | $25.00 |
| Wayne | 3 | $31.05 | 19 | $30.50 |
| Haywood | 3 | $25.00 | 13 | $24.20 |
| Cumberland | 3 | $17.50 | 12 | $22.38 |
| Henderson | 4 | $55.66 | 12 | $44.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 2 to 120 | 24 | $39.00 |
| 130 to 520 | 24 | $24.59 |
| 525 to 1,400 | 24 | $23.48 |
| 1,420 to 39,550 | 24 | $15.12 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 OCT 2026 | C205216 | Martin | 380 | $20.00 | $24.88 | 4 | BARNHILL CONTRACTING CO | NCDOT |
| 20 OCT 2026 | C204338 | Wake | 2,790 | $14.73 | $20.48 | 8 | BLYTHE CONSTRUCTION INC | NCDOT |
| 24 SEP 2026 | C205140 | New Hanover | 45 | $119.86 | $119.86 | 1 | BALFOUR BEATTY INFRASTRUCTURE INC | NCDOT |
| 15 SEP 2026 | C205203 | Wayne | 141 | $35.00 | $32.50 | 6 | LEGION ASPHALT INC | NCDOT |
| 15 SEP 2026 | C204990 | Randolph | 1,348 | $25.98 | $20.00 | 9 | APAC ATLANTIC INC THOMPSON ARTHUR DIVISION | NCDOT |
| 15 SEP 2026 | C205214 | Wilkes | 145 | $8.50 | $8.50 | 5 | JAMES R VANNOY & SONS CONSTRUCTION COMPANY, LLC | NCDOT |
| 15 SEP 2026 | C204947 | Caldwell | 210 | $14.00 | $23.50 | 3 | BRANCH CIVIL INC | NCDOT |
| 18 AUG 2026 | C205195 | Catawba | 700 | $12.00 | $26.62 | 4 | BLYTHE DEVELOPMENT LLC | NCDOT |
| 18 AUG 2026 | C205205 | Robeson | 6,190 | $12.00 | $8.10 | 2 | BMCO CONSTRUCTION INC | NCDOT |
| 18 AUG 2026 | C205202 | Guilford | 440 | $16.00 | $23.20 | 5 | TRIANGLE GRADING & PAVING INC | NCDOT |
| 18 AUG 2026 | C204504 | Watauga | 3,554 | $24.00 | $24.00 | 3 | BRANCH CIVIL INC | NCDOT |
| 18 AUG 2026 | C205070 | Rutherford | 130 | $24.00 | $23.90 | 9 | UNITED INFRASTRUCTURE GROUP INC | NCDOT |
| 16 JUN 2026 | C205160 | Forsyth | 60 | $15.00 | $34.30 | 5 | BLYTHE CONSTRUCTION INC | NCDOT |
| 16 JUN 2026 | C205182 | Carteret | 11,905 | $18.00 | $14.00 | 2 | BARNHILL CONTRACTING CO | NCDOT |
| 16 JUN 2026 | C204970 | Brunswick | 1,880 | $12.00 | $20.00 | 7 | BARNHILL CONTRACTING CO | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way