Low bidders on NCDOT contracts carried a median of $9.32 per LF for item 0141000000-E, berm ditch construction, over the 24 months to 20 OCT 2026, across 13 low bids. Half of all 83 bids fell between $6.75 and $13.65.

Owner
North Carolina DOT
Item
0141000000-E
Unit
LF
Latest letting
18 AUG 2026
$9.32Low bidder's median, per LF
$9.00Median of all bids, per LF
13Contracts in the window

By year of letting

Berm ditch construction, NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20131111$3.4567$4.40
20141313$4.0098$3.35
20151010$3.0074$4.00
201655$5.8533$5.00
20171010$2.0878$5.00
20181212$4.2064$4.55
201977$4.2036$4.95
202011$4.004$5.25
202166$6.6034$7.27
202277$8.5226$9.78
20231010$9.4341$10.80
202466$11.3129$10.70
202599$8.6057$9.00
202644$11.3826$9.00
Berm ditch construction, NCDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Berm ditch construction, NCDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
110 to 1703$27.20
220 to 6203$10.00
700 to 1,5203$8.60
1,970 to 2,7004$8.75
Berm ditch construction, NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NCDOT contracts carrying Berm ditch construction
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
18 AUG 2026C205195Catawba220$10.00$7.504BLYTHE DEVELOPMENT LLCNCDOT
18 AUG 2026C204504Watauga1,190$12.75$13.303BRANCH CIVIL INCNCDOT
19 MAY 2026C204773Gaston, Mecklenburg170$9.32$10.7910ZACHRY CONSTRUCTION CORPORATIONNCDOT
17 MAR 2026C205013Mecklenburg450$25.00$7.009MOUNTAINEER CONTRACTORS INC AND SUBSIDIARIESNCDOT
18 NOV 2025C205126Buncombe1,520$2.05$11.008BRANCH CIVIL INCNCDOT
18 NOV 2025C205086Jackson110$27.20$12.504BUCHANAN AND SONS INCNCDOT
21 OCT 2025C205093Davie2,620$8.51$9.5010BRANCH CIVIL INCNCDOT
16 SEP 2025C204836Clay1,970$9.00$28.303WATSON CONTRACTING INCNCDOT
20 MAY 2025C205032Chatham2,700$4.50$6.7512FSC II LLC DBA FRED SMITH COMPANYNCDOT
18 MAR 2025C204933Chatham700$8.60$9.1212BARNHILL CONTRACTING CONCDOT
18 FEB 2025C204940Richmond110$46.00$30.003BARNHILL CONTRACTING CONCDOT
14 FEB 2025C205077Haywood2,300$19.44$19.441AMES CONSTRUCTION INCNCDOT
21 JAN 2025C204992Hoke620$6.40$5.704BARNHILL CONTRACTING CONCDOT
15 OCT 2024C204348Iredell, Catawba140$70.00$12.005BLYTHE DEVELOPMENT LLCNCDOT
20 AUG 2024C204937Henderson180$20.00$7.624TENNOCA CONSTRUCTION COMPANYNCDOT
Latest NCDOT contracts carrying Berm ditch construction

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy