Proof rolling unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $300.00 per HR for item 0192000000-N, proof rolling, over the 24 months to 20 OCT 2026, across 15 low bids. Half of all 98 bids fell between $226.25 and $400.00.
- Owner
- North Carolina DOT
- Item
- 0192000000-N
- Unit
- HR
- Latest letting
- 18 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 19 | 19 | $185.00 | 125 | $200.00 |
| 2014 | 15 | 15 | $200.00 | 114 | $197.12 |
| 2015 | 12 | 12 | $200.00 | 76 | $175.81 |
| 2016 | 8 | 8 | $252.50 | 47 | $180.00 |
| 2017 | 10 | 10 | $196.35 | 60 | $195.13 |
| 2018 | 16 | 16 | $208.08 | 91 | $250.00 |
| 2019 | 8 | 8 | $312.50 | 37 | $250.00 |
| 2020 | 1 | 1 | $300.00 | 4 | $284.00 |
| 2021 | 6 | 6 | $261.50 | 30 | $249.00 |
| 2022 | 11 | 11 | $250.00 | 41 | $285.00 |
| 2023 | 9 | 9 | $387.63 | 40 | $352.50 |
| 2024 | 5 | 5 | $330.00 | 27 | $330.00 |
| 2025 | 9 | 9 | $270.00 | 62 | $300.00 |
| 2026 | 6 | 6 | $301.50 | 36 | $287.50 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (HR) | Low bids | Low-bid median |
|---|---|---|
| 3 to 10 | 3 | $250.00 |
| 10 to 10 | 4 | $337.50 |
| 10 to 30 | 4 | $268.30 |
| 30 to 100 | 4 | $397.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 AUG 2026 | C205195 | Catawba | 10 | $275.00 | $386.50 | 4 | BLYTHE DEVELOPMENT LLC | NCDOT |
| 16 JUN 2026 | C204970 | Brunswick | 10 | $303.00 | $300.00 | 7 | BARNHILL CONTRACTING CO | NCDOT |
| 19 MAY 2026 | C205187 | Cumberland | 10 | $200.00 | $350.00 | 4 | HIGHLAND PAVING CO LLC | NCDOT |
| 17 MAR 2026 | C205038 | Wake | 10 | $300.00 | $273.51 | 6 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 17 FEB 2026 | C205095 | Mecklenburg | 10 | $375.00 | $235.75 | 10 | BLYTHE DEVELOPMENT LLC | NCDOT |
| 20 JAN 2026 | C205117 | Cabarrus | 10 | $500.00 | $300.00 | 5 | NJR GROUP INC | NCDOT |
| 21 OCT 2025 | C205093 | Davie | 20 | $189.00 | $225.00 | 10 | BRANCH CIVIL INC | NCDOT |
| 16 SEP 2025 | C204971 | Guilford | 40 | $270.00 | $270.00 | 3 | BLYTHE CONSTRUCTION INC | NCDOT |
| 19 AUG 2025 | C204975 | Forsyth | 5 | $450.00 | $450.00 | 3 | BLYTHE CONSTRUCTION INC | NCDOT |
| 19 AUG 2025 | C205039 | Mecklenburg | 10 | $250.00 | $375.00 | 7 | J T RUSSELL & SONS INC | NCDOT |
| 15 JUL 2025 | C205072 | New Hanover, Pender | 90 | $450.00 | $380.83 | 7 | S T WOOTEN CORPORATION | NCDOT |
| 17 JUN 2025 | C204798 | Guilford | 3 | $200.00 | $325.00 | 4 | TRIANGLE GRADING & PAVING INC | NCDOT |
| 20 MAY 2025 | C205032 | Chatham | 30 | $350.00 | $292.50 | 12 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 18 MAR 2025 | C204933 | Chatham | 30 | $261.60 | $255.80 | 12 | BARNHILL CONTRACTING CO | NCDOT |
| 21 JAN 2025 | C204992 | Hoke | 100 | $444.00 | $270.00 | 4 | BARNHILL CONTRACTING CO | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.