6" concrete walk unit price, Ohio
Low bidders on ODOT contracts carried a median of $19.00 per SF for item 608E13000, 6" concrete walk, over the 24 months to 12 NOV 2026, across 17 low bids. Half of all 61 bids fell between $11.50 and $20.00.
- Owner
- Ohio DOT
- Item
- 608E13000
- Unit
- SF
- Latest letting
- 29 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 4 | 5 | $8.90 | 15 | $9.00 |
| 2021 | 11 | 11 | $7.00 | 45 | $8.00 |
| 2022 | 9 | 9 | $12.00 | 38 | $11.30 |
| 2023 | 13 | 13 | $12.00 | 40 | $12.00 |
| 2024 | 7 | 7 | $13.00 | 18 | $13.75 |
| 2025 | 11 | 11 | $20.00 | 37 | $18.32 |
| 2026 | 6 | 6 | $11.38 | 24 | $12.12 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 20 to 87 | 4 | $51.00 |
| 90 to 172 | 4 | $14.16 |
| 180 to 1,354 | 4 | $19.25 |
| 1,633 to 15,682 | 5 | $10.75 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 OCT 2026 | 260399 | CUY | 15,682 | $10.00 | $10.00 | 4 | TRI-MOR CORP | ODOT |
| 15 OCT 2026 | 260484 | GAL | 10,933 | $10.75 | $14.00 | 3 | ALLARD EXCAVATION LLC | ODOT |
| 25 JUN 2026 | 268012 | VAN | 488 | $19.50 | $20.48 | 3 | PERRAM ELECTRIC INC | ODOT |
| 23 APR 2026 | 268009 | SUM | 1,633 | $12.00 | $14.50 | 5 | KENMORE CONSTRUCTION CO INC | ODOT |
| 19 FEB 2026 | 260090 | MOT | 180 | $12.25 | $12.00 | 5 | Performance Site Development | ODOT |
| 05 FEB 2026 | 260003 | MAH | 172 | $10.00 | $13.50 | 4 | SHELLY & SANDS INC | ODOT |
| 18 DEC 2025 | 254033 | KNO | 1,896 | $20.00 | $19.51 | 3 | CRAWFORD CONSTRUCTION COMPANY INC | ODOT |
| 13 NOV 2025 | 250531 | MUS | 55 | $40.00 | $40.00 | 3 | NLS PAVING, INC | ODOT |
| 13 NOV 2025 | 250538 | AUG | 60 | $62.00 | $35.00 | 4 | ADVANCED EXCAVATING & DEMOLITION LLC | ODOT |
| 09 OCT 2025 | 250404 | HAM | 1,354 | $19.00 | $18.25 | 3 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 25 SEP 2025 | 250428 | BRO | 20 | $70.00 | $70.00 | 1 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 25 SEP 2025 | 250442 | TRU | 91 | $9.00 | $11.00 | 3 | MARUCCI & GAFFNEY EXCAVATING CO | ODOT |
| 08 MAY 2025 | 250269 | JEF | 985 | $20.00 | $17.50 | 5 | LMS CONSTRUCTION INC | ODOT |
| 24 APR 2025 | 250220 | MAD | 87 | $22.00 | $17.00 | 2 | DOUBLE Z CONSTRUCTION COMPANY | ODOT |
| 27 MAR 2025 | 250167 | TUS | 2,282 | $8.30 | $10.00 | 5 | SHELLY COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.