Advance radar detection unit price, Ohio
Low bidders on ODOT contracts carried a median of $10,177 per EACH for item 809E69000, advance radar detection, over the 24 months to 12 NOV 2026, across 4 low bids. Half of all 10 bids fell between $10,001 and $10,350.
- Owner
- Ohio DOT
- Item
- 809E69000
- Unit
- EACH
- Latest letting
- 11 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 29 | 30 | $7,582.50 | 121 | $7,750.00 |
| 2021 | 24 | 26 | $7,392.00 | 101 | $7,415.00 |
| 2022 | 12 | 12 | $7,715.00 | 36 | $8,300.00 |
| 2023 | 7 | 7 | $9,784.50 | 18 | $9,685.00 |
| 2024 | 5 | 5 | $9,410.00 | 8 | $9,613.80 |
| 2025 | 2 | 2 | $10,002 | 4 | $9,675.00 |
| 2026 | 2 | 2 | $12,844 | 6 | $10,350 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| LIC | 6 | $8,650.00 | 21 | $8,300.00 |
| CLE | 6 | $7,347.50 | 20 | $8,000.00 |
| MAH | 5 | $7,150.00 | 19 | $7,500.00 |
| POR | 3 | $7,300.00 | 17 | $7,300.00 |
| MOT | 6 | $7,900.00 | 15 | $7,850.00 |
| CLI | 3 | $7,000.00 | 14 | $7,940.00 |
| MIA | 4 | $7,607.00 | 12 | $7,830.00 |
| FRA | 4 | $9,492.25 | 11 | $9,200.00 |
| CLA | 3 | $7,600.00 | 9 | $7,700.50 |
| FAI | 3 | $7,000.00 | 8 | $7,856.00 |
| District 7 | 5 | $10,004 | 5 | $10,004 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 21 | $7,740.00 |
| 2 to 4 | 21 | $7,900.00 |
| 4 to 4 | 21 | $7,500.00 |
| 4 to 56 | 21 | $9,050.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 11 JUN 2026 | 260297 | District 7 | 4 | $15,338 | $15,338 | 1 | CAPITAL ELECTRIC LINE BUILDERS INC | ODOT |
| 23 APR 2026 | 260211 | POR | 2 | $10,350 | $10,350 | 5 | SHELLY & SANDS INC | ODOT |
| 13 NOV 2025 | 250535 | STA | 2 | $10,000 | $9,350.00 | 3 | KENMORE CONSTRUCTION CO INC | ODOT |
| 17 JUL 2025 | 250352 | District 7 | 4 | $10,004 | $10,004 | 1 | CAPITAL ELECTRIC LINE BUILDERS INC | ODOT |
| 22 AUG 2024 | 240405 | MIA | 4 | $9,410.00 | $9,410.00 | 1 | WALLS BROS ASPHALT CO INC | ODOT |
| 11 JUL 2024 | 240367 | District 7 | 4 | $10,138 | $10,138 | 1 | CAPITAL ELECTRIC LINE BUILDERS INC | ODOT |
| 13 JUN 2024 | 240323 | DAR | 4 | $9,050.00 | $9,433.80 | 2 | BARRETT PAVING MATERIALS INC | ODOT |
| 21 MAR 2024 | 240147 | MOT | 2 | $9,080.00 | $9,140.00 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 11 JAN 2024 | 230596 | FRA | 4 | $10,000 | $9,950.00 | 2 | SHELLY & SANDS INC | ODOT |
| 12 OCT 2023 | 230457 | CLE | 6 | $10,206 | $9,720.00 | 3 | SUNESIS CONSTRUCTION CO | ODOT |
| 13 JUL 2023 | 230390 | District 7 | 8 | $9,977.40 | $9,977.40 | 1 | CAPITAL ELECTRIC LINE BUILDERS INC | ODOT |
| 11 MAY 2023 | 230305 | District 3 | 2 | $8,416.00 | $8,416.00 | 1 | PERRAM ELECTRIC INC | ODOT |
| 27 APR 2023 | 230255 | FRA | 6 | $9,784.50 | $9,784.50 | 4 | SHELLY & SANDS INC | ODOT |
| 09 MAR 2023 | 230174 | LIC | 2 | $10,003 | $9,850.00 | 5 | MILLER BROS CONST INC | ODOT |
| 12 JAN 2023 | 230019 | MAR | 4 | $9,650.00 | $9,075.00 | 2 | SHELLY & SANDS INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.