Anchor assembly, mgs type e (nchrp 350 or mash 201 unit price, Ohio
Low bidders on ODOT contracts carried a median of $2,475.00 per EACH for item 606E26150, anchor assembly, mgs type e (nchrp 350 or mash 201, over the 24 months to 12 NOV 2026, across 4 low bids. Half of all 11 bids fell between $2,422.50 and $2,675.00.
- Owner
- Ohio DOT
- Item
- 606E26150
- Unit
- EACH
- Latest letting
- 28 AUG 2025
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 20 | 20 | $2,312.50 | 114 | $2,400.00 |
| 2021 | 15 | 15 | $2,500.00 | 72 | $2,571.14 |
| 2022 | 24 | 24 | $2,797.50 | 90 | $2,795.00 |
| 2023 | 13 | 13 | $2,500.00 | 50 | $2,550.00 |
| 2024 | 3 | 3 | $2,800.00 | 9 | $2,900.00 |
| 2025 | 4 | 4 | $2,475.00 | 11 | $2,500.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| BEL | 6 | $2,510.00 | 33 | $2,646.00 |
| HOL | 4 | $3,188.46 | 33 | $2,975.00 |
| TUS | 4 | $2,667.50 | 28 | $2,680.00 |
| PRE | 6 | $2,455.00 | 23 | $2,460.00 |
| District 5 | 9 | $2,520.00 | 20 | $2,535.00 |
| CLI | 4 | $2,797.52 | 16 | $2,745.00 |
| COL | 3 | $2,825.00 | 15 | $3,000.00 |
| LIC | 3 | $2,280.00 | 13 | $2,280.00 |
| District 11 | 6 | $2,360.00 | 13 | $2,320.00 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 19 | $2,500.00 |
| 1 to 3 | 20 | $2,700.00 |
| 3 to 8 | 20 | $2,525.00 |
| 10 to 298 | 20 | $2,465.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 AUG 2025 | 250376 | CLI | 4 | $2,500.00 | $2,510.00 | 4 | EAGLE BRIDGE CO | ODOT |
| 26 JUN 2025 | 250329 | District 5 | 60 | $2,820.00 | $2,820.00 | 3 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 13 FEB 2025 | 250003 | MUS | 7 | $2,450.00 | $2,415.00 | 2 | SHELLY COMPANY | ODOT |
| 13 FEB 2025 | 250111 | District 11 | 42 | $2,395.00 | $2,317.50 | 2 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 31 OCT 2024 | 240486 | COL | 2 | $2,800.00 | $3,000.00 | 6 | S E T INC | ODOT |
| 27 JUN 2024 | 240354 | District 5 | 60 | $2,820.00 | $2,685.00 | 2 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 22 FEB 2024 | 240159 | District 11 | 298 | $2,395.00 | $2,395.00 | 1 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 14 DEC 2023 | 230599 | MIA | 2 | $2,500.00 | $2,500.00 | 5 | BRUMBAUGH CONSTRUCTION INC | ODOT |
| 14 DEC 2023 | 230601 | PER | 43 | $2,450.00 | $2,450.00 | 1 | SHELLY COMPANY | ODOT |
| 26 OCT 2023 | 230523 | PIK | 3 | $2,500.00 | $2,510.00 | 4 | D G M INC | ODOT |
| 28 SEP 2023 | 230478 | PRE | 7 | $2,460.00 | $2,460.00 | 3 | EAGLE BRIDGE CO | ODOT |
| 24 AUG 2023 | 230441 | District 5 | 60 | $2,520.00 | $2,660.00 | 2 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 10 AUG 2023 | 230407 | WAR | 1 | $2,550.00 | $2,550.00 | 5 | DOUBLE Z CONSTRUCTION COMPANY | ODOT |
| 11 MAY 2023 | 230304 | WYA | 4 | $2,400.00 | $2,400.00 | 3 | D2 EXCAVATING LLC | ODOT |
| 13 APR 2023 | 230228 | PER | 2 | $2,700.00 | $2,700.00 | 4 | AXIS CIVIL CONSTRUCTION LLC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way