Asphalt concrete intermediate course, 19 mm, type unit price, Ohio
Low bidders on ODOT contracts carried a median of $216.00 per CY for item 442E10100, asphalt concrete intermediate course, 19 mm, type, over the 24 months to 12 NOV 2026, across 30 low bids. Half of all 96 bids fell between $212.30 and $275.75.
- Owner
- Ohio DOT
- Item
- 442E10100
- Unit
- CY
- Latest letting
- 12 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 24 | 24 | $135.72 | 72 | $160.00 |
| 2021 | 24 | 27 | $165.00 | 132 | $177.00 |
| 2022 | 18 | 22 | $202.50 | 79 | $210.00 |
| 2023 | 14 | 13 | $226.00 | 39 | $250.00 |
| 2024 | 8 | 8 | $220.00 | 19 | $255.00 |
| 2025 | 12 | 12 | $201.06 | 30 | $214.95 |
| 2026 | 16 | 16 | $231.00 | 63 | $250.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 160 to 548 | 7 | $275.00 |
| 630 to 2,333 | 8 | $211.00 |
| 2,475 to 5,700 | 7 | $200.00 |
| 6,111 to 24,472 | 8 | $209.45 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260521 | GUE | 160 | $330.00 | $330.00 | 8 | SHELLY & SANDS INC | ODOT |
| 29 OCT 2026 | 260399 | CUY | 1,264 | $360.00 | $343.50 | 4 | TRI-MOR CORP | ODOT |
| 29 OCT 2026 | 260477 | ATB | 3,310 | $230.00 | $245.00 | 3 | KARVO COMPANIES INC | ODOT |
| 15 OCT 2026 | 260484 | GAL | 1,713 | $226.25 | $226.25 | 3 | ALLARD EXCAVATION LLC | ODOT |
| 01 OCT 2026 | 260440 | AUG | 2,610 | $230.00 | $244.00 | 5 | HELMS AND SONS EXCAVATING | ODOT |
| 30 JUL 2026 | 268015 | PRE | 529 | $301.40 | $287.50 | 6 | R B JERGENS CONTRACTORS INC | ODOT |
| 21 MAY 2026 | 260268 | JAC | 526 | $255.00 | $265.50 | 4 | SHELLY & SANDS INC | ODOT |
| 07 MAY 2026 | 260248 | SAN | 2,475 | $250.00 | $250.00 | 3 | GREAT LAKES DEMOLITION COMPANY | ODOT |
| 17 APR 2026 | 268004 | SUM | 548 | $273.06 | $215.00 | 3 | ANTHONY ALLEGA CEMENT CONTRACTOR INC | ODOT |
| 09 APR 2026 | 268005 | MED | 2,333 | $206.00 | $235.00 | 3 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 26 MAR 2026 | 260076 | MAH | 24,472 | $232.00 | $232.00 | 3 | KARVO COMPANIES INC | ODOT |
| 26 MAR 2026 | 260148 | FRA | 499 | $291.00 | $291.00 | 3 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 12 MAR 2026 | 260141 | ROS | 170 | $195.00 | $303.00 | 4 | SHELLY & SANDS INC | ODOT |
| 12 MAR 2026 | 260141 | ROS | 1,241 | $176.00 | $200.00 | 4 | SHELLY & SANDS INC | ODOT |
| 12 MAR 2026 | 268003 | AUG | 1,253 | n/a | $222.66 | 1 | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way