Asphalt concrete intermediate course, 19 mm, type unit price, Ohio
Low bidders on ODOT contracts carried a median of $232.00 per CY for item 442E20200, asphalt concrete intermediate course, 19 mm, type, over the 24 months to 12 NOV 2026, across 9 low bids. Half of all 25 bids fell between $232.00 and $320.00.
- Owner
- Ohio DOT
- Item
- 442E20200
- Unit
- CY
- Latest letting
- 07 MAY 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 16 | 18 | $177.50 | 68 | $203.19 |
| 2021 | 23 | 27 | $273.00 | 97 | $260.00 |
| 2022 | 13 | 13 | $229.02 | 47 | $250.00 |
| 2023 | 6 | 7 | $260.00 | 18 | $295.00 |
| 2024 | 4 | 4 | $290.00 | 15 | $250.00 |
| 2025 | 5 | 5 | $225.00 | 15 | $268.00 |
| 2026 | 4 | 4 | $260.00 | 10 | $260.00 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 07 MAY 2026 | 260239 | HAR | 323 | $250.00 | $250.00 | 3 | EAGLE BRIDGE CO | ODOT |
| 07 MAY 2026 | 260252 | WAS | 464 | $270.00 | $259.00 | 2 | ALAN STONE CO INC | ODOT |
| 26 MAR 2026 | 260158 | WOO | 1,084 | $200.00 | $196.50 | 2 | GERKEN PAVING INC | ODOT |
| 29 JAN 2026 | 260001 | CUY | 14 | $680.00 | $680.00 | 3 | RUHLIN COMPANY | ODOT |
| 18 DEC 2025 | 250557 | HAM | 407 | $320.00 | $385.00 | 4 | EAGLE BRIDGE CO | ODOT |
| 13 NOV 2025 | 250522 | GAL | 6,538 | $216.25 | $216.25 | 1 | SHELLY COMPANY | ODOT |
| 17 JUL 2025 | 250338 | ATH | 2,269 | $225.00 | $225.00 | 1 | SHELLY & SANDS INC | ODOT |
| 27 MAR 2025 | 250159 | HAR | 637 | $232.00 | $230.20 | 2 | HELMS AND SONS EXCAVATING | ODOT |
| 30 JAN 2025 | 250060 | MOT | 950 | $200.00 | $268.00 | 7 | BARRETT PAVING MATERIALS INC | ODOT |
| 31 OCT 2024 | 240505 | SUM | 75 | $500.00 | $2,270.00 | 3 | KARVO COMPANIES INC | ODOT |
| 04 APR 2024 | 240212 | HAM | 34 | $275.00 | $755.00 | 3 | ADLETA INC | ODOT |
| 08 FEB 2024 | 240087 | FRA | 105 | $305.00 | $229.00 | 3 | SHELLY & SANDS INC | ODOT |
| 25 JAN 2024 | 240079 | WYA | 1,425 | $219.00 | $209.00 | 6 | HELMS AND SONS EXCAVATING | ODOT |
| 10 AUG 2023 | 230420 | PRE | 102 | $260.00 | $242.50 | 2 | EAGLE BRIDGE CO | ODOT |
| 20 APR 2023 | 230175 | SUM | 2,342 | $245.00 | $265.00 | 5 | RUHLIN-GREAT LAKES SR 8 -JOINT VENTURE | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.