Asphalt concrete intermediate course, type 1, (449 unit price, Ohio
Low bidders on ODOT contracts carried a median of $375.50 per CY for item 441E70200, asphalt concrete intermediate course, type 1, (449, over the 24 months to 12 NOV 2026, across 38 low bids. Half of all 128 bids fell between $300.00 and $607.50.
- Owner
- Ohio DOT
- Item
- 441E70200
- Unit
- CY
- Latest letting
- 29 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 11 | 11 | $266.00 | 32 | $295.00 |
| 2023 | 20 | 20 | $387.50 | 69 | $430.00 |
| 2024 | 17 | 19 | $250.00 | 69 | $310.00 |
| 2025 | 19 | 18 | $387.50 | 63 | $350.00 |
| 2026 | 15 | 16 | $405.00 | 53 | $455.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| BRO | 3 | $398.00 | 12 | $360.00 |
| LIC | 3 | $341.00 | 9 | $341.00 |
| GUE | 3 | $260.00 | 5 | $260.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 10 | 9 | $500.00 |
| 14 to 43 | 10 | $399.00 |
| 45 to 142 | 9 | $377.00 |
| 159 to 678 | 10 | $300.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 OCT 2026 | 260454 | ADA | 25 | $477.00 | $477.00 | 5 | D G M INC | ODOT |
| 29 OCT 2026 | 260456 | COL | 85 | $446.00 | $566.75 | 2 | SHELLY & SANDS INC | ODOT |
| 01 OCT 2026 | 260424 | FAI | 261 | $300.00 | $390.00 | 2 | SHELLY COMPANY | ODOT |
| 13 AUG 2026 | 260363 | HAS | 14 | $865.00 | $865.00 | 5 | J D WILLIAMSON CONSTRUCTION CO INC | ODOT |
| 30 JUL 2026 | 260356 | MIA | 1 | $500.00 | $1,537.50 | 2 | WALLS BROS ASPHALT CO INC | ODOT |
| 25 JUN 2026 | 260305 | BRO | 306 | $238.00 | $291.68 | 5 | FILLMORE CONSTRUCTION | ODOT |
| 21 MAY 2026 | 260270 | LAW | 128 | $410.00 | $329.00 | 3 | ALAN STONE CO INC | ODOT |
| 07 MAY 2026 | 260261 | MIA | 4 | $400.00 | $437.50 | 2 | BRUMBAUGH CONSTRUCTION INC | ODOT |
| 07 MAY 2026 | 268008 | HAM | 243 | $300.00 | $377.50 | 4 | SUNESIS CONSTRUCTION CO | ODOT |
| 26 MAR 2026 | 260149 | HAM | 43 | $830.00 | $765.00 | 4 | SUNESIS CONSTRUCTION CO | ODOT |
| 26 MAR 2026 | 260155 | LIC | 253 | $341.00 | $341.00 | 3 | RIETSCHLIN CONSTRUCTION INC | ODOT |
| 26 MAR 2026 | 260155 | LIC | 25 | $374.00 | $374.00 | 3 | RIETSCHLIN CONSTRUCTION INC | ODOT |
| 26 MAR 2026 | 260157 | STA | 6 | $720.00 | $900.00 | 5 | RUHLIN COMPANY | ODOT |
| 12 MAR 2026 | 260098 | SUM | 36 | $265.00 | $265.00 | 3 | BLACK HORSE BRIDGE CONSTRUCTION INC | ODOT |
| 12 MAR 2026 | 264007 | GUE | 3 | $2,887.50 | $2,887.50 | 1 | BCC OHIO INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.