Asphalt concrete intermediate course, type 2, (446 unit price, Ohio
Low bidders on ODOT contracts carried a median of $175.00 per CY for item 441E10200, asphalt concrete intermediate course, type 2, (446, over the 24 months to 12 NOV 2026, across 25 low bids. Half of all 81 bids fell between $168.00 and $225.00.
- Owner
- Ohio DOT
- Item
- 441E10200
- Unit
- CY
- Latest letting
- 01 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 13 | 17 | $129.00 | 53 | $144.00 |
| 2021 | 19 | 19 | $132.00 | 66 | $139.50 |
| 2022 | 15 | 15 | $170.00 | 41 | $180.00 |
| 2023 | 12 | 13 | $170.84 | 31 | $175.00 |
| 2024 | 10 | 11 | $198.00 | 34 | $209.80 |
| 2025 | 14 | 13 | $170.00 | 39 | $179.65 |
| 2026 | 11 | 11 | $192.50 | 39 | $206.75 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 10 to 2,232 | 6 | $223.38 |
| 2,439.60 to 3,860 | 6 | $167.50 |
| 3,999 to 5,989 | 6 | $172.00 |
| 6,923 to 18,776 | 7 | $175.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 01 OCT 2026 | 260405 | DEL | 8,070 | $205.00 | $184.50 | 3 | SHELLY & SANDS INC | ODOT |
| 13 AUG 2026 | 260368 | PIK | 488 | $240.00 | $250.00 | 9 | ALLARD EXCAVATION LLC | ODOT |
| 13 AUG 2026 | 260373 | WIL | 3,630 | $192.50 | $192.50 | 1 | GERKEN PAVING INC | ODOT |
| 30 JUL 2026 | 268015 | PRE | 123 | $290.82 | $277.50 | 6 | R B JERGENS CONTRACTORS INC | ODOT |
| 23 APR 2026 | 260211 | POR | 18,776 | $163.00 | $163.00 | 5 | SHELLY & SANDS INC | ODOT |
| 09 APR 2026 | 260133 | PIC | 757 | $206.75 | $229.38 | 2 | SHELLY COMPANY | ODOT |
| 09 APR 2026 | 260171 | COL | 7,193 | $180.00 | $174.00 | 2 | SHELLY & SANDS INC | ODOT |
| 19 FEB 2026 | 260095 | SAN | 4,622 | $152.00 | $164.00 | 3 | ERIE BLACKTOP INC | ODOT |
| 19 FEB 2026 | 260109 | HOL | 5,989 | $160.00 | $175.00 | 4 | SHELLY & SANDS INC | ODOT |
| 29 JAN 2026 | 260045 | CAR | 8,320 | $165.00 | $180.00 | 3 | SHELLY COMPANY | ODOT |
| 15 JAN 2026 | 260039 | LAW | 10 | $1,925.00 | $1,925.00 | 1 | SHELLY COMPANY | ODOT |
| 04 DEC 2025 | 250556 | GEA | 4,663 | $200.00 | $200.00 | 3 | KARVO COMPANIES INC | ODOT |
| 23 OCT 2025 | 250489 | CLI | 6,981 | $179.65 | $189.82 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 09 OCT 2025 | 250457 | BUT | 3,860 | $228.00 | $218.41 | 2 | BARRETT PAVING MATERIALS INC | ODOT |
| 09 OCT 2025 | 250465 | HOL | 6,923 | $175.00 | $195.00 | 3 | MELWAY PAVING CO INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way