Borrow unit price, Ohio
Low bidders on ODOT contracts carried a median of $50.00 per CY for item 203E40000, borrow, over the 24 months to 12 NOV 2026, across 5 low bids. Half of all 15 bids fell between $50.00 and $68.00.
- Owner
- Ohio DOT
- Item
- 203E40000
- Unit
- CY
- Latest letting
- 19 FEB 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 17 | 30 | $100.00 | 146 | $100.00 |
| 2021 | 11 | 18 | $67.29 | 87 | $77.10 |
| 2022 | 9 | 16 | $200.00 | 64 | $200.00 |
| 2023 | 10 | 17 | $200.00 | 52 | $200.00 |
| 2024 | 4 | 4 | $64.00 | 10 | $58.00 |
| 2025 | 4 | 4 | $50.00 | 14 | $55.00 |
| 2026 | 1 | 1 | $65.00 | 1 | $65.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| MAH | 17 | $125.00 | 70 | $125.00 |
| POR | 10 | $175.00 | 56 | $150.00 |
| STA | 11 | $105.00 | 47 | $105.00 |
| TRU | 10 | $83.78 | 42 | $65.00 |
| SUM | 9 | $200.00 | 30 | $200.00 |
| District 4 | 5 | $200.00 | 29 | $200.00 |
| ATB | 8 | $186.00 | 26 | $161.00 |
| District 11 | 7 | $64.00 | 14 | $64.00 |
| District 9 | 3 | $50.00 | 8 | $51.00 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 2 to 5 | 22 | $159.00 |
| 5 to 10 | 23 | $200.00 |
| 12 to 32 | 22 | $115.75 |
| 50 to 9,006 | 23 | $64.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 19 FEB 2026 | 260083 | District 11 | 50 | $65.00 | $65.00 | 1 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 04 DEC 2025 | 250562 | MAH | 5 | $50.00 | $50.00 | 3 | SHELLY COMPANY | ODOT |
| 09 OCT 2025 | 250455 | AUG | 12 | $30.00 | $50.00 | 5 | JUTTE EXCAVATING INC | ODOT |
| 13 FEB 2025 | 250111 | District 11 | 50 | $64.00 | $66.00 | 2 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 16 JAN 2025 | 250033 | District 9 | 1,732 | $50.00 | $55.00 | 4 | PDK CONSTRUCTION INC | ODOT |
| 08 AUG 2024 | 240395 | TRU | 10 | $150.00 | $150.00 | 3 | SHELLY & SANDS INC | ODOT |
| 09 MAY 2024 | 240289 | WOO | 5,971 | $20.00 | $20.00 | 4 | GREAT LAKES DEMOLITION COMPANY | ODOT |
| 22 FEB 2024 | 240159 | District 11 | 50 | $64.00 | $64.00 | 1 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 08 FEB 2024 | 240118 | District 9 | 5,373 | $64.00 | $58.00 | 2 | PDK CONSTRUCTION INC | ODOT |
| 09 NOV 2023 | 230550 | STA | 18 | $142.17 | $142.17 | 3 | KARVO COMPANIES INC | ODOT |
| 09 NOV 2023 | 230554 | WOO | 3,714 | $28.72 | $32.00 | 5 | E S WAGNER COMPANY | ODOT |
| 12 OCT 2023 | 230484 | ATB | 20 | $172.00 | $100.00 | 3 | KARVO COMPANIES INC | ODOT |
| 12 OCT 2023 | 230484 | ATB | 5 | $400.00 | $400.00 | 3 | KARVO COMPANIES INC | ODOT |
| 28 SEP 2023 | 230458 | ATB | 20 | $200.00 | $200.00 | 2 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 27 JUL 2023 | 230403 | MAH | 10 | $250.00 | $250.00 | 2 | SHELLY & SANDS INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way