Chevron marking unit price, Ohio

Low bidders on ODOT contracts carried a median of $11.50 per FT for item 646E10620, chevron marking, over the 24 months to 12 NOV 2026, across 40 low bids. Half of all 121 bids fell between $10.00 and $14.00.

Owner
Ohio DOT
Item
646E10620
Unit
FT
Latest letting
12 NOV 2026
$11.50Low bidder's median, per FT
$12.50Median of all bids, per FT
40Contracts in the window

By year of letting

Chevron marking, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201617$9.5054$9.38
20211514$11.0059$10.00
20221415$15.0057$12.50
20231818$12.7559$12.50
202488$11.6219$12.00
20251414$11.5046$11.75
20262323$12.0070$12.50
Chevron marking, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Chevron marking, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
CUY11$10.0035$11.75
HAM6$81.3814$14.25
SUM3$10.0011$10.00
Chevron marking, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Chevron marking, ODOT: low bidder's median by quantity band
Quantity (FT)Low bidsLow-bid median
29 to 6110$12.00
70 to 15010$11.25
151 to 33510$13.00
427 to 1,00010$10.00
Chevron marking, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Chevron marking
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260489ASD492$9.00$9.002SHELLY & SANDS INCODOT
29 OCT 2026260468MAH46$11.00$11.254SHELLY & SANDS INCODOT
15 OCT 2026260473TUS297$11.00$11.502SHELLY & SANDS INCODOT
15 OCT 2026260482District 1134$6.00$12.754AAD CONTRACTING INCODOT
08 OCT 2026260398HAM40$165.14$165.141JOHN R JURGENSEN COMPANYODOT
13 AUG 2026260345CUY29$12.00$22.304GREAT LAKES CONSTRUCTION COODOT
30 JUL 2026260327CUY254$14.50$14.503RUHLIN COMPANYODOT
30 JUL 2026264019District 485$22.00$27.502B & G TRUCKING & CONSTRUCTION INCODOT
11 JUN 2026260285CUY471$7.00$7.003KARVO COMPANIES INCODOT
21 MAY 2026260264CRA170$13.00$13.502PAVEMENT MAINTENANCE SYSTEMS LLCODOT
07 MAY 2026260231CUY116$5.00$5.002KARVO COMPANIES INCODOT
07 MAY 2026260237FRA43$12.50$12.502SHELLY & SANDS INCODOT
07 MAY 2026260251MOT335$14.25$14.252JOHN R JURGENSEN COMPANYODOT
07 MAY 2026260258District 1250$12.00$16.003PERRAM ELECTRIC INCODOT
17 APR 2026268004SUM86$7.22$7.223ANTHONY ALLEGA CEMENT CONTRACTOR INCODOT
Latest ODOT contracts carrying Chevron marking

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy