Detectable warning, as per plan unit price, Ohio

Low bidders on ODOT contracts carried a median of $70.00 per SF for item 608E53021, detectable warning, as per plan, over the 24 months to 12 NOV 2026, across 11 low bids. Half of all 26 bids fell between $65.00 and $78.53.

Owner
Ohio DOT
Item
608E53021
Unit
SF
Latest letting
29 OCT 2026
$70.00Low bidder's median, per SF
$70.00Median of all bids, per SF
9Contracts in the window

By year of letting

Detectable warning, as per plan, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201212$60.0064$69.75
20211010$35.5031$61.50
202299$30.0032$31.91
202344$106.0013$100.00
202466$72.0019$71.72
202555$65.0015$65.00
202635$144.608$127.30
Detectable warning, as per plan, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

Latest contracts with this item

Latest ODOT contracts carrying Detectable warning, as per plan
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
29 OCT 2026260456COL20$44.00$51.252SHELLY & SANDS INCODOT
07 MAY 2026260232CUY40$200.00$200.003PERK COMPANY INCODOT
23 APR 2026260194BEL125$239.44$239.441GRAE-CON CONSTRUCTION INCODOT
23 APR 2026260194BEL20$144.60$144.601GRAE-CON CONSTRUCTION INCODOT
23 APR 2026260194BEL85$74.14$74.141GRAE-CON CONSTRUCTION INCODOT
23 OCT 2025250486BEL101$71.00$71.003SHELLY & SANDS INCODOT
25 SEP 2025250433COL164$45.00$62.504NLS PAVING, INCODOT
11 SEP 2025250411HAM520$65.00$65.005FORD DEVELOPMENT CORPODOT
17 JUL 2025250348RIC22$70.00$70.001SHELLY & SANDS INCODOT
22 MAY 2025250278HAM550$55.00$50.002COMPLETE GENERAL CONSTRUCTION COMPANYODOT
14 NOV 2024240528JEF443$70.00$72.503SHELLY & SANDS INCODOT
26 SEP 2024240432COL34$37.50$45.003SHELLY & SANDS INCODOT
12 SEP 2024240415BEL397$80.00$73.003NLS PAVING, INCODOT
04 APR 2024240223ATH10$170.00$94.002SHELLY & SANDS INCODOT
21 MAR 2024240185MRW424$74.00$74.002SHELLY & SANDS INCODOT
Latest ODOT contracts carrying Detectable warning, as per plan

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy