Dumped rock fill, type c unit price, Ohio
Low bidders on ODOT contracts carried a median of $305.10 per CY for item 601E27000, dumped rock fill, type c, over the 24 months to 12 NOV 2026, across 8 low bids. Half of all 22 bids fell between $211.50 and $376.20.
- Owner
- Ohio DOT
- Item
- 601E27000
- Unit
- CY
- Latest letting
- 07 MAY 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 16 | 39 | $150.00 | 166 | $125.00 |
| 2021 | 8 | 12 | $158.90 | 59 | $189.38 |
| 2022 | 9 | 9 | $135.00 | 25 | $150.00 |
| 2023 | 10 | 15 | $400.00 | 47 | $350.00 |
| 2024 | 5 | 5 | $350.00 | 21 | $250.00 |
| 2025 | 3 | 7 | $376.20 | 15 | $376.20 |
| 2026 | 1 | 1 | $125.00 | 7 | $210.00 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 07 MAY 2026 | 260244 | MUS | 9 | $125.00 | $210.00 | 7 | BUDS INC | ODOT |
| 14 AUG 2025 | 250379 | HAS | 27 | $219.00 | $216.00 | 3 | OHIO-WEST VIRGINIA EXCAVATING CO | ODOT |
| 08 MAY 2025 | 250239 | ATB | 8 | $234.00 | $217.00 | 2 | RONYAK PAVING INC | ODOT |
| 08 MAY 2025 | 250239 | ATB | 6 | $234.00 | $242.00 | 2 | RONYAK PAVING INC | ODOT |
| 13 FEB 2025 | 250080 | ATB | 5 | $376.20 | $376.20 | 2 | KARVO COMPANIES INC | ODOT |
| 13 FEB 2025 | 250080 | ATB | 5 | $376.20 | $376.20 | 2 | KARVO COMPANIES INC | ODOT |
| 13 FEB 2025 | 250080 | ATB | 5 | $376.20 | $376.20 | 2 | KARVO COMPANIES INC | ODOT |
| 13 FEB 2025 | 250080 | ATB | 5 | $376.20 | $376.20 | 2 | KARVO COMPANIES INC | ODOT |
| 31 OCT 2024 | 240458 | ATH | 226 | $90.00 | $106.00 | 9 | D G M INC | ODOT |
| 08 AUG 2024 | 240395 | TRU | 9 | $350.00 | $350.00 | 3 | SHELLY & SANDS INC | ODOT |
| 13 JUN 2024 | 240332 | SUM | 5 | $400.00 | $400.00 | 3 | KARVO COMPANIES INC | ODOT |
| 21 MAR 2024 | 240171 | District 4 | 5 | $400.00 | $325.00 | 2 | B & G TRUCKING & CONSTRUCTION INC | ODOT |
| 22 FEB 2024 | 240151 | TRU | 70 | $250.00 | $250.00 | 4 | SHELLY & SANDS INC | ODOT |
| 09 NOV 2023 | 230550 | STA | 7 | $252.75 | $252.75 | 3 | KARVO COMPANIES INC | ODOT |
| 28 SEP 2023 | 230462 | District 7 | 282 | $145.00 | $145.00 | 3 | BRUMBAUGH CONSTRUCTION INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.