Emulsion, chip seal unit price, Ohio
Low bidders on ODOT contracts carried a median of $3.12 per GAL for item 422E25000, emulsion, chip seal, over the 24 months to 12 NOV 2026, across 27 low bids. Half of all 86 bids fell between $3.05 and $4.42.
- Owner
- Ohio DOT
- Item
- 422E25000
- Unit
- GAL
- Latest letting
- 01 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 16 | 16 | $2.44 | 61 | $2.75 |
| 2021 | 12 | 12 | $2.97 | 37 | $3.15 |
| 2022 | 14 | 14 | $3.20 | 55 | $3.40 |
| 2023 | 18 | 18 | $3.50 | 54 | $3.45 |
| 2024 | 12 | 12 | $3.23 | 37 | $3.15 |
| 2025 | 17 | 17 | $3.10 | 52 | $3.27 |
| 2026 | 5 | 5 | $3.43 | 20 | $4.05 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| ROS | 4 | $4.37 | 19 | $4.45 |
| District 10 | 4 | $3.11 | 6 | $3.20 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (GAL) | Low bids | Low-bid median |
|---|---|---|
| 119 to 11,548 | 6 | $5.25 |
| 25,106 to 40,706 | 7 | $3.10 |
| 45,218 to 57,606 | 7 | $3.24 |
| 59,053 to 199,134 | 7 | $3.10 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 01 OCT 2026 | 260436 | SCI | 36,694 | $3.43 | $3.65 | 5 | RUNWAY INCORPORATED | ODOT |
| 30 JUL 2026 | 260350 | HAS | 36,314 | $4.35 | $4.05 | 4 | SAORSA CONSTRUCTION OHIO, INC. | ODOT |
| 25 JUN 2026 | 260310 | CUY | 25,106 | $2.00 | $3.00 | 4 | RONYAK PAVING INC | ODOT |
| 23 APR 2026 | 260222 | ROS | 6,151 | $5.50 | $4.65 | 5 | FILLMORE CONSTRUCTION | ODOT |
| 19 FEB 2026 | 260093 | PER | 40,706 | $3.05 | $4.25 | 2 | SHELLY COMPANY | ODOT |
| 18 DEC 2025 | 250561 | LAK | 7,162 | $2.90 | $2.90 | 7 | SPECIALIZED CONSTRUCTION INC | ODOT |
| 18 DEC 2025 | 250596 | ROS | 57,606 | $3.24 | $3.50 | 5 | RUNWAY INCORPORATED | ODOT |
| 13 NOV 2025 | 250516 | CLE | 55,191 | $3.25 | $3.25 | 3 | RUNWAY INCORPORATED | ODOT |
| 23 OCT 2025 | 250491 | GUE | 115,221 | $2.92 | $3.11 | 2 | SHELLY COMPANY | ODOT |
| 23 OCT 2025 | 250506 | WAR | 31,348 | $3.07 | $3.25 | 5 | SHELLY COMPANY | ODOT |
| 25 SEP 2025 | 250433 | COL | 45,218 | $3.55 | $3.35 | 4 | NLS PAVING, INC | ODOT |
| 11 SEP 2025 | 250408 | District 10 | 199,134 | $3.12 | $3.33 | 2 | SHELLY COMPANY | ODOT |
| 11 SEP 2025 | 250409 | GEA | 56,349 | $2.75 | $2.75 | 1 | RONYAK PAVING INC | ODOT |
| 11 SEP 2025 | 250416 | SCI | 53,016 | $3.05 | $3.44 | 2 | SHELLY COMPANY | ODOT |
| 28 AUG 2025 | 250392 | District 10 | 130,541 | $3.10 | $3.35 | 2 | SHELLY COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.