Excavation, as per plan unit price, Ohio

Low bidders on ODOT contracts carried a median of $33.90 per CY for item 203E10001, excavation, as per plan, over the 24 months to 12 NOV 2026, across 37 low bids. Half of all 138 bids fell between $25.00 and $61.10.

Owner
Ohio DOT
Item
203E10001
Unit
CY
Latest letting
12 NOV 2026
$33.90Low bidder's median, per CY
$35.00Median of all bids, per CY
37Contracts in the window

By year of letting

Excavation, as per plan, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201919$18.50115$21.00
20211313$30.0054$27.73
20221616$26.2554$36.63
20231820$34.7556$42.00
20241617$40.0042$47.47
20251818$32.5071$40.00
20261818$34.4564$33.95
Excavation, as per plan, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Excavation, as per plan, ODOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
3 to 369$60.00
40 to 1979$30.00
215 to 9509$35.00
1,340 to 241,83810$22.00
Excavation, as per plan, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Excavation, as per plan
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260524WAR510$35.00$40.007PRUS CONSTRUCTION COMPANYODOT
29 OCT 2026260467LAW241,838$25.00$26.002ALLARD EXCAVATION LLCODOT
29 OCT 2026260476WOO115$20.00$20.007GREAT LAKES DEMOLITION COMPANYODOT
08 OCT 2026260398HAM73$534.41$534.411JOHN R JURGENSEN COMPANYODOT
01 OCT 2026260451WYA2,228$19.00$33.008ADVANCED EXCAVATING & DEMOLITION LLCODOT
25 JUN 2026260307COS446$32.00$31.004COMPLETE GENERAL CONSTRUCTION COMPANYODOT
25 JUN 2026260319FRA619$69.00$69.003RUHLIN COMPANYODOT
25 JUN 2026268013RIC3$364.00$352.002EIUS COMPANYODOT
11 JUN 2026260293CUY215$66.00$162.003RUHLIN COMPANYODOT
07 MAY 2026260167ERI3,635$15.00$15.503GREAT LAKES DEMOLITION COMPANYODOT
07 MAY 2026260251MOT5,102$45.72$40.362JOHN R JURGENSEN COMPANYODOT
23 APR 2026260142MEG197$18.00$20.754CAST & BAKER CORPORATIONODOT
23 APR 2026260209MOT362$131.20$93.602DOUBLE JAY CONSTRUCTION INCODOT
26 MAR 2026260146District 1240$65.00$65.001LAKE ERIE CONSTRUCTION COMPANYODOT
12 MAR 2026264007GUE30$17.20$17.201BCC OHIO INCODOT
Latest ODOT contracts carrying Excavation, as per plan

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy