Fog seal unit price, Ohio

Low bidders on ODOT contracts carried a median of $3.20 per GAL for item 886E11000, fog seal, over the 24 months to 12 NOV 2026, across 21 low bids. Half of all 56 bids fell between $3.05 and $4.00.

Owner
Ohio DOT
Item
886E11000
Unit
GAL
Latest letting
01 OCT 2026
$3.20Low bidder's median, per GAL
$3.33Median of all bids, per GAL
21Contracts in the window

By year of letting

Fog seal, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201010$2.9831$3.50
202166$2.6212$2.80
202299$2.8530$2.95
20231212$3.1629$3.25
202444$3.429$3.50
20251515$3.1538$3.17
202644$3.1313$3.50
Fog seal, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Fog seal, ODOT: low bidder's median by quantity band
Quantity (GAL)Low bidsLow-bid median
330 to 11,7555$5.00
12,898 to 18,3325$3.21
19,078 to 21,4945$3.15
23,354 to 80,7316$3.10
Fog seal, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Fog seal
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
01 OCT 2026260436SCI14,840$3.21$3.505RUNWAY INCORPORATEDODOT
30 JUL 2026260350HAS14,722$2.75$3.404SAORSA CONSTRUCTION OHIO, INC.ODOT
25 JUN 2026260318ERI1,052$5.00$6.502HENRY W BERGMAN INCODOT
19 FEB 2026260093PER16,503$3.05$3.272SHELLY COMPANYODOT
18 DEC 2025250596ROS23,354$2.57$3.005RUNWAY INCORPORATEDODOT
04 DEC 2025250568PIC3,616$4.00$4.332KOKOSING CONSTRUCTION COMPANY INCODOT
13 NOV 2025250516CLE20,696$2.89$2.893RUNWAY INCORPORATEDODOT
23 OCT 2025250491GUE46,713$2.85$2.982SHELLY COMPANYODOT
23 OCT 2025250506WAR11,755$3.20$3.205SHELLY COMPANYODOT
25 SEP 2025250433COL18,332$3.55$3.354NLS PAVING, INCODOT
25 SEP 2025250451ERI817$15.00$14.502ERIE BLACKTOP INCODOT
11 SEP 2025250408District 1080,731$3.15$3.402SHELLY COMPANYODOT
11 SEP 2025250409GEA21,131$4.00$4.001RONYAK PAVING INCODOT
11 SEP 2025250416SCI21,494$3.15$3.062SHELLY COMPANYODOT
28 AUG 2025250392District 1052,925$3.15$3.252SHELLY COMPANYODOT
Latest ODOT contracts carrying Fog seal

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy