Ground rod unit price, Ohio

Low bidders on ODOT contracts carried a median of $300.00 per EACH for item 625E32000, ground rod, over the 24 months to 12 NOV 2026, across 228 low bids. Half of all 769 bids fell between $260.00 and $350.00.

Owner
Ohio DOT
Item
625E32000
Unit
EACH
Latest letting
12 NOV 2026
$300.00Low bidder's median, per EACH
$300.00Median of all bids, per EACH
190Contracts in the window

By year of letting

Ground rod, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202084103$252.53438$254.48
2021121147$260.00670$261.50
2022104134$304.88487$306.00
202389112$319.00390$320.00
20247284$300.00305$300.00
202592114$300.00382$300.00
202690105$325.00355$300.00
Ground rod, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Ground rod, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
CUY20$309.5060$300.00
FRA21$325.0055$325.00
HAM17$265.0049$300.00
MOT10$286.0041$300.00
FAI7$275.0033$275.00
TRU5$200.0032$245.00
MAH8$200.0030$255.68
SUM7$250.0022$255.00
District 36$319.5021$310.00
MIA3$125.8219$255.00
AUG4$382.5016$337.50
WAR3$385.0015$314.00
Ground rod, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Ground rod, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 457$310.00
4 to 957$325.00
10 to 2057$275.00
20 to 18057$286.00
Ground rod, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Ground rod
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260495COL2$200.00$328.003CORNERSTONE ELECTRIC INCODOT
12 NOV 2026260513BEL25$250.00$250.001SHELLY & SANDS INCODOT
12 NOV 2026260515District 36$329.00$314.502PERRAM ELECTRIC INCODOT
12 NOV 2026260516District 7107$363.00$345.404DANBERT ELECTRICAL CORPODOT
12 NOV 2026260521GUE25$451.00$451.008SHELLY & SANDS INCODOT
12 NOV 2026260524WAR48$385.00$320.417PRUS CONSTRUCTION COMPANYODOT
29 OCT 2026260399CUY11$180.00$220.504TRI-MOR CORPODOT
29 OCT 2026260399CUY7$400.00$387.504TRI-MOR CORPODOT
29 OCT 2026260399CUY26$180.00$220.504TRI-MOR CORPODOT
29 OCT 2026260453DEL4$750.00$750.003SHELLY & SANDS INCODOT
29 OCT 2026260455ASD2$302.57$302.572KOKOSING CONSTRUCTION COMPANY INCODOT
29 OCT 2026260468MAH11$200.00$225.684SHELLY & SANDS INCODOT
29 OCT 2026260468MAH5$200.00$197.504SHELLY & SANDS INCODOT
29 OCT 2026260477ATB59$164.68$200.003KARVO COMPANIES INCODOT
15 OCT 2026260484GAL30$411.00$425.003ALLARD EXCAVATION LLCODOT
Latest ODOT contracts carrying Ground rod

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy