Guardrail, type mgs half post spacing, as per plan unit price, Ohio
Low bidders on ODOT contracts carried a median of $35.25 per FT for item 606E15151, guardrail, type mgs half post spacing, as per plan, over the 24 months to 12 NOV 2026, across 6 low bids. Half of all 23 bids fell between $32.00 and $48.75.
- Owner
- Ohio DOT
- Item
- 606E15151
- Unit
- FT
- Latest letting
- 01 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 10 | 10 | $28.00 | 63 | $31.00 |
| 2021 | 6 | 6 | $34.00 | 33 | $38.80 |
| 2022 | 9 | 10 | $38.50 | 45 | $37.60 |
| 2023 | 4 | 4 | $35.95 | 14 | $37.40 |
| 2024 | 6 | 6 | $35.50 | 16 | $35.00 |
| 2025 | 3 | 3 | $30.00 | 12 | $32.00 |
| 2026 | 3 | 3 | $41.40 | 11 | $48.50 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| BEL | 21 | $37.00 | 111 | $37.50 |
| HOL | 3 | $39.00 | 24 | $39.20 |
| FRA | 7 | $28.00 | 14 | $27.00 |
| JEF | 3 | $32.40 | 14 | $32.75 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 50 to 131.25 | 10 | $29.00 |
| 137.50 to 237.50 | 11 | $35.00 |
| 250 to 375 | 10 | $34.70 |
| 375 to 1,425 | 11 | $39.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 01 OCT 2026 | 260418 | ADA | 450 | $54.00 | $54.00 | 5 | ALLARD EXCAVATION LLC | ODOT |
| 11 JUN 2026 | 260300 | FRA | 50 | $35.00 | $33.50 | 2 | M P DORY CO | ODOT |
| 15 JAN 2026 | 260008 | BEL | 275 | $41.40 | $45.20 | 4 | SHELLY & SANDS INC | ODOT |
| 14 AUG 2025 | 250386 | FRA | 50 | $30.00 | $31.00 | 2 | M P DORY CO | ODOT |
| 27 FEB 2025 | 250115 | BEL | 287.50 | $30.00 | $30.00 | 5 | ALAN STONE CO INC | ODOT |
| 16 JAN 2025 | 250037 | HOL | 212.50 | $35.50 | $37.00 | 5 | SHELLY & SANDS INC | ODOT |
| 26 SEP 2024 | 240441 | HAN | 175 | $34.44 | $34.44 | 3 | BCC OHIO INC | ODOT |
| 26 SEP 2024 | 240451 | BEL | 187.50 | $35.00 | $35.00 | 5 | ALAN STONE CO INC | ODOT |
| 11 JUL 2024 | 240371 | MAH | 150 | $38.00 | $38.00 | 1 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 13 JUN 2024 | 240338 | FRA | 50 | $28.00 | $30.00 | 2 | M P DORY CO | ODOT |
| 18 APR 2024 | 240250 | BEL | 375 | $36.00 | $38.00 | 4 | DENNISON BRIDGE INC | ODOT |
| 22 FEB 2024 | 240159 | District 11 | 50 | $68.00 | $68.00 | 1 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 08 JUN 2023 | 230354 | JEF | 350 | $32.40 | $35.00 | 3 | SHELLY & SANDS INC | ODOT |
| 08 JUN 2023 | 230359 | FRA | 50 | $28.00 | $26.80 | 2 | M P DORY CO | ODOT |
| 27 APR 2023 | 230250 | BEL | 262.50 | $42.00 | $39.00 | 5 | DENNISON BRIDGE INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.