Linear grading, as per plan unit price, Ohio

Low bidders on ODOT contracts carried a median of $8,390.00 per MI for item 209E60501, linear grading, as per plan, over the 24 months to 12 NOV 2026, across 8 low bids. Half of all 24 bids fell between $8,160.00 and $14,521.

Owner
Ohio DOT
Item
209E60501
Unit
MI
Latest letting
23 APR 2026
$8,390.00Low bidder's median, per MI
$10,000Median of all bids, per MI
8Contracts in the window

By year of letting

Linear grading, as per plan, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202055$1,250.0022$2,300.00
20211111$1,500.0048$1,850.00
2022109$3,400.0024$2,095.00
20231010$2,350.0038$2,000.00
202455$10,00014$10,250
202555$8,500.0016$10,973
202622$5,390.006$9,140.00
Linear grading, as per plan, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

Latest contracts with this item

Latest ODOT contracts carrying Linear grading, as per plan
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
23 APR 2026260203HUR6.96$8,280.00$10,0003MARK HAYNES CONSTRUCTION INCODOT
26 MAR 2026260076MAH5.62$2,500.00$7,800.003KARVO COMPANIES INCODOT
23 OCT 2025250504MUS20.39$8,500.00$9,000.003SHELLY COMPANYODOT
11 SEP 2025250410GUE20.75$8,800.00$7,650.002SHELLY & SANDS INCODOT
15 MAY 2025250251HAM2$2,500.00$14,3615RACK & BALLAUER EXCAVATING CO INCODOT
30 JAN 2025250048GEA6.02$1,000.00$1,287.502RONYAK PAVING INCODOT
30 JAN 2025250074MRG0.29$12,445$20,0004SHELLY & SANDS INCODOT
19 DEC 2024240578GUE12.81$10,000$10,2502SHELLY & SANDS INCODOT
26 SEP 2024240443HAS0.08$8,190.00$17,5004BCC OHIO INCODOT
13 JUN 2024240327GUE12.12$15,000$9,750.002SHELLY & SANDS INCODOT
09 MAY 2024240282STA1.50$20,000$11,0004SHELLY COMPANYODOT
08 FEB 2024240111WAS4.22$650.00$2,325.002SHELLY & SANDS INCODOT
14 DEC 2023230592CUY3.87$850.00$1,425.004SHELLY COMPANYODOT
26 OCT 2023230519GEA2.96$2,200.00$2,200.005COLE BURTON CONTRACTORS, LLCODOT
12 OCT 2023230502WAS0.84$2,900.00$2,900.001SHELLY & SANDS INCODOT
Latest ODOT contracts carrying Linear grading, as per plan

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy