Monument box adjusted to grade unit price, Ohio
Low bidders on ODOT contracts carried a median of $675.00 per EACH for item 623E39500, monument box adjusted to grade, from 23 JAN 2020 to 09 NOV 2023, across 130 low bids. Half of all 390 bids fell between $500.00 and $900.00.
- Owner
- Ohio DOT
- Item
- 623E39500
- Unit
- EACH
- Latest letting
- 09 NOV 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 51 | 51 | $700.00 | 164 | $625.00 |
| 2021 | 44 | 44 | $600.00 | 122 | $600.00 |
| 2022 | 22 | 23 | $830.00 | 70 | $800.00 |
| 2023 | 12 | 12 | $942.50 | 34 | $1,000.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| CUY | 10 | $625.00 | 52 | $637.50 |
| LOR | 6 | $667.50 | 27 | $725.00 |
| FRA | 7 | $720.00 | 24 | $675.00 |
| LAK | 3 | $450.00 | 21 | $455.95 |
| WOO | 7 | $725.00 | 18 | $750.00 |
| OTT | 4 | $637.50 | 11 | $725.00 |
| LUC | 5 | $850.00 | 11 | $790.00 |
| TUS | 3 | $1,500.00 | 10 | $800.00 |
| HAM | 5 | $1,300.00 | 10 | $1,147.95 |
| HEN | 4 | $850.00 | 8 | $1,000.00 |
| ERI | 4 | $600.00 | 8 | $650.00 |
| MOT | 4 | $522.50 | 8 | $558.55 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 32 | $725.00 |
| 1 to 3 | 33 | $700.00 |
| 3 to 5 | 32 | $687.50 |
| 5 to 40 | 33 | $625.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 09 NOV 2023 | 230553 | TUS | 8 | $1,500.00 | $1,250.00 | 2 | SHELLY & SANDS INC | ODOT |
| 27 JUL 2023 | 230402 | LUC | 1 | $1,957.10 | $1,353.55 | 2 | GERKEN PAVING INC | ODOT |
| 13 JUL 2023 | 238005 | HEN | 3 | $1,450.00 | $1,450.00 | 1 | GERKEN PAVING INC | ODOT |
| 08 JUN 2023 | 230363 | WYA | 4 | $1,500.00 | $1,500.00 | 3 | SHELLY & SANDS INC | ODOT |
| 25 MAY 2023 | 230331 | OTT | 2 | $1,000.00 | $1,000.00 | 3 | GERKEN PAVING INC | ODOT |
| 11 MAY 2023 | 230291 | HEN | 2 | $300.00 | $1,100.00 | 3 | VERNON NAGEL INC | ODOT |
| 30 MAR 2023 | 230178 | CUY | 10 | $650.00 | $1,050.00 | 3 | SHELLY COMPANY | ODOT |
| 30 MAR 2023 | 230195 | TRU | 1 | $100.00 | $900.00 | 6 | SHELLY & SANDS INC | ODOT |
| 09 MAR 2023 | 230116 | CRA | 5 | $800.00 | $700.00 | 2 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 09 MAR 2023 | 230144 | CUY | 1 | $700.00 | $675.00 | 4 | COOK PAVING & CONSTRUCTION CO INC | ODOT |
| 09 MAR 2023 | 230149 | FAY | 4 | $1,148.08 | $1,148.08 | 1 | JOHN R JURGENSEN COMPANY | ODOT |
| 09 MAR 2023 | 230150 | FRA | 5 | $885.00 | $1,142.50 | 4 | SHELLY COMPANY | ODOT |
| 14 APR 2022 | 220228 | ALL | 6 | $950.00 | $775.00 | 2 | GERKEN PAVING INC | ODOT |
| 14 APR 2022 | 220236 | FRA | 1 | $1,480.00 | $1,140.00 | 2 | SHELLY & SANDS INC | ODOT |
| 14 APR 2022 | 220244 | LOR | 3 | $725.00 | $725.00 | 5 | KARVO COMPANIES INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way