Pavement planing, asphalt concrete, 3" unit price, Ohio
Low bidders on ODOT contracts carried a median of $10.00 per SY for item 254E01000, pavement planing, asphalt concrete, 3", over the 24 months to 12 NOV 2026, across 22 low bids. Half of all 93 bids fell between $5.00 and $24.13.
- Owner
- Ohio DOT
- Item
- 254E01000
- Unit
- SY
- Latest letting
- 01 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 9 | 9 | $7.50 | 30 | $14.88 |
| 2021 | 12 | 12 | $3.62 | 40 | $5.07 |
| 2022 | 14 | 15 | $2.95 | 48 | $4.03 |
| 2023 | 17 | 17 | $4.90 | 51 | $12.00 |
| 2024 | 15 | 15 | $8.00 | 51 | $8.50 |
| 2025 | 13 | 13 | $13.75 | 63 | $13.75 |
| 2026 | 6 | 6 | $4.35 | 21 | $5.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 57 to 267 | 5 | $30.00 |
| 321 to 804 | 6 | $17.62 |
| 890 to 10,204 | 5 | $9.00 |
| 26,213 to 72,784 | 6 | $2.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 01 OCT 2026 | 260439 | WAR | 3,813 | $3.50 | $6.48 | 3 | FILLMORE CONSTRUCTION | ODOT |
| 13 AUG 2026 | 260373 | WIL | 65,338 | $2.65 | $2.65 | 1 | GERKEN PAVING INC | ODOT |
| 07 MAY 2026 | 260226 | ALL | 804 | $3.70 | $4.00 | 3 | FENSON CONTRACTING LLC | ODOT |
| 26 MAR 2026 | 260155 | LIC | 321 | $10.00 | $10.00 | 3 | RIETSCHLIN CONSTRUCTION INC | ODOT |
| 29 JAN 2026 | 260057 | LAK | 26,213 | $5.00 | $5.00 | 7 | GEAUGA HIGHWAY CO | ODOT |
| 15 JAN 2026 | 260008 | BEL | 345 | $25.00 | $25.00 | 4 | SHELLY & SANDS INC | ODOT |
| 04 DEC 2025 | 250565 | MER | 561 | $18.00 | $18.00 | 3 | BRUMBAUGH CONSTRUCTION INC | ODOT |
| 13 NOV 2025 | 250517 | CLE | 125 | $29.11 | $29.55 | 10 | BCC OHIO INC | ODOT |
| 13 NOV 2025 | 250521 | FAI | 968 | $9.00 | $10.50 | 7 | SHELLY & SANDS INC | ODOT |
| 25 SEP 2025 | 250432 | CLI | 29,978 | $2.00 | $2.00 | 3 | FILLMORE CONSTRUCTION | ODOT |
| 25 SEP 2025 | 250443 | UNI | 267 | $30.00 | $15.25 | 4 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 25 SEP 2025 | 250445 | WOO | 57 | $30.00 | $30.00 | 7 | E S WAGNER COMPANY | ODOT |
| 11 SEP 2025 | 250411 | HAM | 6,531 | $13.75 | $12.50 | 5 | FORD DEVELOPMENT CORP | ODOT |
| 11 SEP 2025 | 250417 | SEN | 72,784 | $2.50 | $2.83 | 4 | M & B ASPHALT CO INC | ODOT |
| 22 MAY 2025 | 250285 | SEN | 40,164 | $0.91 | $2.38 | 4 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way